11200 W SATICOY ST 91352
Certificate Information: 11200 W SATICOY ST 91352
- Application / Permit
- 22014-20000-04560
- Plan Check / Job No.
- B22VN13782
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING AND INTERIOR REMODEL, fire sprinkler system is required
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2022 | MINA HABILI |
| Corrections Issued | 9/15/2022 | MINA HABILI |
| Plan Check Approved | 11/30/2022 | MINA HABILI |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 10/25/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 11/13/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/13/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/18/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 12/8/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 12/8/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/12/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 2/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 2/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/9/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/13/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 2/20/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 2/22/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/7/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 7/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/20/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 8/28/2024 | Approved | JOSE AVILA |
| Service/Power Release | 8/28/2024 | Approved | JOSE AVILA |
| HVAC-Final | 9/19/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/24/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |