9007 N BAIRD AVE 91324

Certificate Information: 9007 N BAIRD AVE 91324

Application / Permit
22014-20000-04556
Plan Check / Job No.
B22VN13770
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION TO (E) SFD W/ ATTACHED GARAGE
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
CofO Issued on 10/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2022 APPLICANT
Assigned to Plan Check Engineer 9/13/2022 FERNANDO FLORES
Corrections Issued 9/13/2022 FERNANDO FLORES
Applicant returned to address corrections 11/26/2022 AUNG SOE
Plan Check Approved 11/30/2022 FERNANDO FLORES
Issued 12/2/2022 APPLICANT
CofO in Progress 9/27/2023 JOHN KIDWELL
Permit Finaled 10/5/2023 JOHN JANSON
CofO Issued 10/5/2023 JOHN JANSON
Permit Finaled 10/5/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/20/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 11/3/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/3/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Lao,, Arturo Begino; Lic. No.: C56687 16348 MIDWOOD DR      GRANADA HILLS, CA 91344

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/24/2023 Approved JOHN KIDWELL
Gas Test 4/24/2023 Partial Approval JOHN KIDWELL
HVAC-Rough 4/24/2023 Approved JOHN KIDWELL
PLUMBING-Rough 4/24/2023 Approved JOHN KIDWELL
Sewer 4/24/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/1/2023 Approved JOHN KIDWELL
Green Building Rough 5/1/2023 Approved JOHN KIDWELL
Insulation 5/1/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/1/2023 Partial Approval JOHN KIDWELL
Wood Frame 5/1/2023 Approved JOHN KIDWELL
Drywall Nailing 5/5/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/18/2023 Partial Approval JOHN KIDWELL
Shower Pan 5/18/2023 Approved JOHN KIDWELL
Final 9/19/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 9/19/2023 Approved JOHN KIDWELL
Green Building Final 9/19/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 9/19/2023 Approved JOHN KIDWELL
Final 9/26/2023 OK to Issue CofO JOHN KIDWELL