2984 N GLENDALE BLVD 90039

Certificate Information: 2984 N GLENDALE BLVD 90039

Application / Permit
22014-20000-04554
Plan Check / Job No.
B22VN13765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE (420 SQFT) TO ADU W/ ADDITION (10'-0"x16'-6"), 205 SQFT. PER LAMC 12.22 A.33(c)(d) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 PETER MOSESIAN
Corrections Issued 10/1/2022 PETER MOSESIAN
Quality Review Completed 10/5/2022 OMID HEDAYAT
Building Plans Picked Up 10/11/2022 APPLICANT
Plan Check Approved 12/14/2022 PETER MOSESIAN
Issued 12/16/2022 APPLICANT
CofO in Progress 1/17/2024 HAMIK HARTOUNIAN
CofO Issued 1/21/2024 DEROLD HAUFF
Permit Finaled 1/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/25/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/27/2022 JEANIE LAM
Sewer availability Cleared 10/27/2022 JEANIE LAM
"Q" conditions Cleared 11/8/2022 DANG NGUYEN
ZI Cleared 11/8/2022 DANG NGUYEN
Low Impact Development Cleared 11/15/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 11/18/2022 AMAAN MALIK
ZI Cleared 12/7/2022 DARBY WHIPPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2023 Approved HAMIK HARTOUNIAN
Underground Mechanical 2/9/2023 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 2/10/2023 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/16/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 5/16/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Approved LILIANA PORTILLO
HVAC-Rough 5/24/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 5/24/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/1/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 6/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 6/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/12/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/12/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 6/12/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/12/2023 Partial Approval HAMIK HARTOUNIAN
MERV13>=Rough 6/12/2023 Approved HAMIK HARTOUNIAN
Insulation 6/28/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/18/2023 Approved HAMIK HARTOUNIAN
Shower Pan 7/18/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 8/11/2023 Approved HAMIK HARTOUNIAN
Shower Pan 8/11/2023 Conditional Approval HAMIK HARTOUNIAN
Final 1/9/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 1/9/2024 Approved HAMIK HARTOUNIAN
MERV13>=Final 1/9/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 1/9/2024 Approved HAMIK HARTOUNIAN
Final 1/17/2024 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 1/17/2024 Approved HAMIK HARTOUNIAN