2982 N GLENDALE BLVD 90039
Certificate Information: 2982 N GLENDALE BLVD 90039
- Application / Permit
- 22014-20000-04553
- Plan Check / Job No.
- B22VN13765
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (19'-7"x50'-5"), 762 SQFT ADDITION TO SFD AND INT REMODEL TO (E) SFD W/NFPA 13D SPRINKLERS REQ THROUGHOUT
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | PETER MOSESIAN |
| Corrections Issued | 10/1/2022 | PETER MOSESIAN |
| Quality Review Completed | 10/5/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 10/11/2022 | APPLICANT |
| Plan Check Approved | 12/14/2022 | PETER MOSESIAN |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 1/17/2024 | HAMIK HARTOUNIAN |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | JEANIE LAM |
| "Q" conditions | Cleared | 11/8/2022 | DANG NGUYEN |
| ZI | Cleared | 11/8/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 11/15/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | AMAAN MALIK |
| ZI | Cleared | 12/7/2022 | DARBY WHIPPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/28/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 1/26/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/10/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/22/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/16/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 5/16/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/24/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/24/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 6/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 6/1/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/12/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 7/7/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/18/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 7/18/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 8/11/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 8/11/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 1/9/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/9/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 1/9/2024 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 1/9/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/9/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 1/17/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |