4241 N LAURELGROVE AVE 91604

Certificate Information: 4241 N LAURELGROVE AVE 91604

Application / Permit
22014-20000-04539
Plan Check / Job No.
B22VN13744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE TO AN ACCESSORY DWELLING UNIT, PER LAMC 12.22 A.33(c) AND (d), AND AN ADDITION OF 7' x 7'4".
Permit Issued
Issued on 7/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 LUIS RINCON
Corrections Issued 9/16/2022 LUIS RINCON
Building Plans Picked Up 9/20/2022 APPLICANT
Applicant returned to address corrections 10/7/2022 RACHEL BEYENE
Plan Check Approved 11/10/2022 KHUONG TRUONG
Issued 7/10/2023 APPLICANT
CofO in Progress 8/14/2025 CHRISTOPHE COCHRAN
Permit Finaled 10/8/2025 RUBEN SALAS
CofO Issued 10/8/2025 RUBEN SALAS
Permit Finaled 10/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/3/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/3/2022 COLIN LOREDO
Sewer availability Cleared 10/4/2022 COLIN LOREDO
Construction near power lines Cleared 11/8/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 11/10/2022 CHRISTOPHER ROCHA

Contact Information

Architect Brouse,, Jon Robert; Lic. No.: C22200 12930 VENTURA BLVD SUITE 214      STUDIO CITY, CA 91604
Contractor Struct 1 Builders Inc; Lic. No.: 792134-B 16217 KITTRIDGE ST      VAN NUYS, CA 91406

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/17/2023 Partial Approval CHRISTOPHE COCHRAN
Gas Test 7/24/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/24/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/15/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/17/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/22/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/20/2023 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 11/20/2023 Approved JOHN COLEMAN
ELECTRICAL-Rough 3/5/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/2/2024 Approved JOHN COLEMAN
Insulation 4/12/2024 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/30/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 5/30/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 5/30/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/30/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/21/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 6/21/2024 Corrections Issued JOHN COLEMAN
Insulation 6/21/2024 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 6/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 6/28/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 6/28/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/28/2024 Approved CHRISTOPHE COCHRAN
Insulation 7/1/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/1/2024 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 7/1/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 7/3/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 7/15/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/16/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 5/27/2025 No Access for Inspection CHRISTOPHE COCHRAN
Green Building Final 5/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 5/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/26/2025 Partial Inspection JAVIER RAMOS JR
Final 6/26/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/26/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/26/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/26/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/11/2025 Approved CHRISTOPHE COCHRAN
Final 8/11/2025 Corrections Issued CHRISTOPHE COCHRAN
Final 8/14/2025 OK to Issue CofO CHRISTOPHE COCHRAN