13611 W DELANO ST 91401

Certificate Information: 13611 W DELANO ST 91401

Application / Permit
22014-20000-04533
Plan Check / Job No.
B22VN13715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION TO (E) SFD W/ ATTACHED GARAGE BUILDING TO BE FULLY SPRINKLERED
Permit Issued
Issued on 10/24/2022
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 FERNANDO FLORES
Corrections Issued 9/17/2022 FERNANDO FLORES
Applicant returned to address corrections 10/5/2022 FERNANDO FLORES
Plan Check Approved 10/19/2022 FERNANDO FLORES
Issued 10/24/2022 APPLICANT
CofO in Progress 4/1/2024 JOSE AVILA
Permit Finaled 4/15/2024 RUBEN SALAS
CofO Issued 4/15/2024 RUBEN SALAS
Permit Finaled 4/15/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/12/2022 CHRIS CHAHBAZ
Low Impact Development Cleared 10/18/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 10/18/2022 CHRIS CHAHBAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316
Engineer Mohammadi,, Saeid; Lic. No.: NA82330       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/9/2022 Approved KIRK SANDERS
Deputy Drilled-In Anchors 12/12/2022 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 12/15/2022 Approved KIRK SANDERS
Deputy Reinf. Concrete 12/19/2022 Conditional Approval ROBERT GOLD
Deputy Wood Construction 2/17/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/17/2023 Corrections Issued KIRK SANDERS
Green Building Rough 3/17/2023 Not Ready for Inspection KIRK SANDERS
Rough-Elec/Plmb/HVAC 3/17/2023 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 3/17/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 3/28/2023 Approved KIRK SANDERS
Green Building Rough 3/28/2023 Approved KIRK SANDERS
Underground Mechanical 3/28/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 3/28/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 4/18/2023 Approved KIRK SANDERS
Insulation 5/2/2023 Approved KIRK SANDERS
Drywall Nailing 5/10/2023 Approved JUAN VALENZUELA
Shower Pan 7/11/2023 No Access for Inspection ROBERT GOLD
Shower Pan 7/17/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/10/2023 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 10/10/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 10/10/2023 Approved CHRISTOPHER ROJAS
Smoke Detectors 10/10/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/18/2023 Approved CHRISTOPHER ROJAS
HVAC-Final 10/18/2023 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Ready KIRK SANDERS
Final 1/10/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 1/10/2024 Approved JOSE AVILA
Green Building Final 1/10/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready JOSE AVILA
Final 1/16/2024 Partial Approval JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved JOSE AVILA
Final 3/29/2024 OK to Issue CofO JOSE AVILA