7843 S BRIGHTON AVE 90047
Certificate Information: 7843 S BRIGHTON AVE 90047
- Application / Permit
- 22014-20000-04508
- Plan Check / Job No.
- B22VN13663
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRR SHAPED 14'9"X24'6" BEDRM, BATH, CLOSET ADDN @ REAR OF EX 1-STORY SFD. ALL WORK PER ENGR DESIGN
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | YAQUB MIRZA |
| Corrections Issued | 9/13/2022 | YAQUB MIRZA |
| Building Plans Picked Up | 9/20/2022 | APPLICANT |
| Plan Check Approved | 11/22/2022 | HAYATO TSUCHIYA |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 3/20/2026 | JOHN QUINTANILLA |
| Permit Finaled | 3/21/2026 | DEROLD HAUFF |
| CofO Issued | 3/21/2026 | DEROLD HAUFF |
| Permit Finaled | 3/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/16/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | WALLIE JONG |
Contact Information
| Contractor | A G A Construction Inc; Lic. No.: 918705-B | 18375 VENTURA BLVD #548 TARZANA, CA 91356 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Pre-Inspection | 1/12/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/27/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/7/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 3/22/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/1/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/1/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/1/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 5/4/2023 | Approved | MICHAEL LEWIS |
| Insulation | 5/12/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/12/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 5/17/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/17/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | STUART CHAPMAN |
| Final | 6/12/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 6/12/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/12/2023 | Approved | STUART CHAPMAN |
| Final | 6/27/2023 | Partial Inspection | MICHAEL LEWIS |
| Final | 3/2/2026 | Corrections Issued | LUIS CASTRO |
| Final | 3/13/2026 | OK to Issue CofO | JOHN QUINTANILLA |