12908-12910 W NEWTON ST 91342

Certificate Information: 12908-12910 W NEWTON ST 91342

Application / Permit
22014-20000-04506
Plan Check / Job No.
B22VN13646
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) ATTACHED GARAGE TO A NEW (22'-0" x 24'-0") ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/19/2022
Issuing Office
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 DANIEL ABRAMYAN
Corrections Issued 9/12/2022 DANIEL ABRAMYAN
Plan Check Approved 9/19/2022 SARKIS HARABEDIAN
Issued 9/19/2022 APPLICANT
CofO in Progress 5/5/2023 ARAM AVEDISIAN
Permit Finaled 5/8/2023 MICHAEL SMITH
CofO Issued 5/8/2023 MICHAEL SMITH
Permit Finaled 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/14/2022 CARLOS AGUILERA
Sewer availability Cleared 9/14/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 9/16/2022 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/28/2022 Corrections Issued ARAM AVEDISIAN
Sewer 9/28/2022 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 10/12/2022 Corrections Issued ARAM AVEDISIAN
Deputy Drilled-In Anchors 10/13/2022 No Result Entered KENNETH KUROWSKI
Footing/Foundation/Slab 10/14/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/7/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/7/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 11/7/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/16/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/16/2022 Approved ARAM AVEDISIAN
Insulation 12/13/2022 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 12/22/2022 Approved ARAM AVEDISIAN
Shower Pan 12/30/2022 Corrections Issued ARAM AVEDISIAN
Shower Pan 1/5/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/24/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/7/2023 Approved ARAM AVEDISIAN
Final 3/7/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 3/7/2023 Approved ARAM AVEDISIAN
Final 5/5/2023 OK to Issue CofO ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved ARAM AVEDISIAN