12908-12910 W NEWTON ST 91342
Certificate Information: 12908-12910 W NEWTON ST 91342
- Application / Permit
- 22014-20000-04506
- Plan Check / Job No.
- B22VN13646
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE TO A NEW (22'-0" x 24'-0") ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 9/12/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/19/2022 | SARKIS HARABEDIAN |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 5/5/2023 | ARAM AVEDISIAN |
| Permit Finaled | 5/8/2023 | MICHAEL SMITH |
| CofO Issued | 5/8/2023 | MICHAEL SMITH |
| Permit Finaled | 5/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/14/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 9/16/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 9/28/2022 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/12/2022 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 10/13/2022 | No Result Entered | KENNETH KUROWSKI |
| Footing/Foundation/Slab | 10/14/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/7/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/7/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 11/7/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/16/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/16/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 12/13/2022 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 12/22/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 12/30/2022 | Corrections Issued | ARAM AVEDISIAN |
| Shower Pan | 1/5/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/24/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/7/2023 | Approved | ARAM AVEDISIAN |
| Final | 3/7/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 3/7/2023 | Approved | ARAM AVEDISIAN |
| Final | 5/5/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Approved | ARAM AVEDISIAN |