11885 W TIARA ST 91607

Certificate Information: 11885 W TIARA ST 91607

Application / Permit
22014-20000-04496
Plan Check / Job No.
B22VN13630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND CONVERT (E) PATIO COVER TO NEW DINNING ROOM TO (E) SINGLE-FAMILY DWELLING AND ADD NEW PATIO COVERED. ALL WORK PER ENGINEER.
Permit Issued
Issued on 4/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 PINANK PATEL
Corrections Issued 9/12/2022 PINANK PATEL
Building Plans Picked Up 9/16/2022 APPLICANT
Plan Check Approved 11/3/2022 LUIS RINCON
Issued 4/11/2023 APPLICANT
CofO in Progress 10/25/2023 JENNIFER RABUCHIN
CofO Issued 1/23/2024 RUBEN SALAS
Permit Finaled 1/23/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/30/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 10/3/2022 FERNANDO GIL

Contact Information

Contractor Az Vision Remodeling; Lic. No.: 1015050-B 11909 TIARA STREET      VALLEY VILLAGE, CA 91607
Engineer Mansuri,, Mehran; Lic. No.: C78614 14944 HESBY ST      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 5/19/2023 Partial Approval JOHN HAYES
Service/Power Release 6/28/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 6/28/2023 Not Ready for Inspection JOHN HAYES
Wood Frame 7/6/2023 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 8/9/2023 Approved JOHN HAYES
PLUMBING-Rough 8/9/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 8/23/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Approved JENNIFER RABUCHIN
Green Building Rough 8/23/2023 Not Ready for Inspection JENNIFER RABUCHIN
Shower Pan 8/23/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/28/2023 Approved JOHN HAYES
Green Building Rough 8/28/2023 Approved JOHN HAYES
Interior/Exterior Lathing 8/28/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 8/28/2023 Approved JOHN HAYES
HVAC-Rough 8/29/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 8/29/2023 Approved JENNIFER RABUCHIN
Insulation 9/1/2023 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/7/2023 Approved JOHN HAYES
ELECTRICAL-Final 10/24/2023 Approved JENNIFER RABUCHIN
Final 10/24/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 10/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/24/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/24/2023 Approved JENNIFER RABUCHIN
Smoke Detectors 10/24/2023 Approved JENNIFER RABUCHIN