9625 N AQUEDUCT AVE 91343
Certificate Information: 9625 N AQUEDUCT AVE 91343
- Application / Permit
- 22014-20000-04491
- Plan Check / Job No.
- B22VN13621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 43'-4" X 8'-4" & 5'-4" X 9'-2"ADDITIONS AND NEW 8'-6" X 21'-9" PATIO COVER ADDITIONS TO (E) 1-STORY SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 8/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 9/13/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| Applicant returned to address corrections | 5/4/2023 | MINA HABILI |
| Applicant returned to address corrections | 5/16/2023 | MINA HABILI |
| Plan Check Approved | 5/25/2023 | LUISANGEL VALENZUELA |
| Issued | 8/29/2023 | APPLICANT |
| CofO in Progress | 6/26/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/17/2023 | KIRK LINKLATER |
| Sewer availability | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 4/17/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/25/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2023 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 10/5/2023 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 7/12/2024 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 7/19/2024 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 7/19/2024 | Partial Inspection | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/1/2024 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 8/1/2024 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 8/23/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 8/29/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 9/11/2024 | Partial Approval | RAUL OLAGI |
| Deputy Other (see comments) | 9/12/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/18/2024 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/25/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/30/2024 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 10/29/2024 | Approved | RAUL OLAGI |
| Final | 10/29/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 10/29/2024 | Approved | RAUL OLAGI |
| Green Building Final | 10/29/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 10/29/2024 | Approved | RAUL OLAGI |
| MERV13>=Final | 10/29/2024 | Approved | RAUL OLAGI |
| MERV13>=Rough | 10/29/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 10/29/2024 | Corrections Issued | RAUL OLAGI |
| Final | 4/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 4/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 6/25/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Smoke Detectors | 6/25/2025 | Approved | SALVADOR MARTINEZ |