1444 N MORAGA DR 90049
Certificate Information: 1444 N MORAGA DR 90049
- Application / Permit
- 22014-20000-04490
- Plan Check / Job No.
- B22VN13615
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2872 SF ADDITION AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | RAPHAEL ROSAS |
| Corrections Issued | 9/19/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 9/23/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/26/2022 | APPLICANT |
| Plan Check Approved | 12/13/2022 | RAPHAEL ROSAS |
| Issued | 1/6/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/29/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/29/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/29/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/29/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/29/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/17/2022 | DINAH GARIN |
| Private street | Cleared | 11/1/2022 | KENTON TRINH |
| Tract Map conditions | Cleared | 11/1/2022 | KENTON TRINH |
| ZA Case | Cleared | 11/1/2022 | KENTON TRINH |
| Low Impact Development | Cleared | 11/23/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/27/2022 | SAUL GARCIA |
| Watercourse | Cleared | 11/28/2022 | HISASHI KOBAYAKAWA |
| Distance to fire station | Cleared | 12/2/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 12/13/2022 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 12/13/2022 | RAPHAEL ROSAS |
Contact Information
| Architect | Elmanovich,, Vladimir; Lic. No.: C25822 | 16987 ENCINO HILLS DRIVE ENCINO, CA 91436 |
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/1/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/9/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/13/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/6/2023 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/24/2023 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/19/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 5/24/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/25/2023 | Partial Approval | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 6/5/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 6/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Structural Steel Frame | 6/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 6/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 7/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/28/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/16/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 10/16/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 10/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 10/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/18/2023 | Corrections Issued | CARLOS MATAMOROS |
| Wood Frame | 10/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 12/7/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/8/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/12/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 4/29/2024 | Partial Inspection | MICHAEL PELHAM |
| HVAC-Rough | 6/20/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/20/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 6/20/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 6/20/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/2/2024 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 7/25/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/9/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 9/18/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/18/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/3/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 10/3/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 10/17/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/30/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/26/2026 | Approved | EVAN COOPER |