13738 N ELDRIDGE AVE 91342
Certificate Information: 13738 N ELDRIDGE AVE 91342
- Application / Permit
- 22014-20000-04482
- Plan Check / Job No.
- B22VN13546
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (244 SF) TO (E) 1-STORY SFD.
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | VIVIAN LAO |
| Corrections Issued | 9/13/2022 | VIVIAN LAO |
| Plan Check Approved | 10/4/2022 | VIVIAN LAO |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 3/29/2023 | ARAM AVEDISIAN |
| CofO Issued | 4/19/2023 | MICHAEL SMITH |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/19/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/7/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/19/2022 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 12/19/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/20/2023 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 1/20/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/24/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/24/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 1/24/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 1/24/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/3/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 2/3/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 2/13/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/23/2023 | Approved | MICHEL ABAJAN |
| Final | 3/23/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/23/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/23/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/29/2023 | Approved | ARAM AVEDISIAN |
| Final | 3/29/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 3/29/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/29/2023 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/29/2023 | Approved | ARAM AVEDISIAN |