14856 W COBALT ST 91342
Certificate Information: 14856 W COBALT ST 91342
- Application / Permit
- 22014-20000-04481
- Plan Check / Job No.
- B22VN13544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached Garage conversion and addition to new ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/21/2022
- Issuing Office
- Current Status
- CofO Issued on 2/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | HANS SANTIAGO |
| Corrections Issued | 9/10/2022 | HANS SANTIAGO |
| Plan Check Approved | 10/10/2022 | ANDREW SANTIAGO |
| Issued | 10/21/2022 | APPLICANT |
| CofO in Progress | 2/6/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
| CofO Issued | 2/23/2024 | RUBEN SALAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 9/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/19/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 10/7/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/6/2023 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/12/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 7/12/2023 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 8/29/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | KEVIN BERBERYAN |
| Gas Test | 8/29/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 8/29/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 8/29/2023 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 8/29/2023 | Approved | KEVIN BERBERYAN |
| Wood Frame | 8/29/2023 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/18/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 9/18/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/21/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/21/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 9/21/2023 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/21/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | ROBERT GOLD |
| Green Building Rough | 9/26/2023 | Approved | ROBERT GOLD |
| Insulation | 9/26/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | ROBERT GOLD |
| Underground Mechanical | 9/26/2023 | Approved | ROBERT GOLD |
| Insulation | 9/27/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/27/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/4/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/16/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 10/16/2023 | Approved | KEVIN BERBERYAN |
| Final | 12/22/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 12/22/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/22/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 2/2/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 2/2/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/2/2024 | Approved | CHRISTOPHER ROJAS |