14856 W COBALT ST 91342

Certificate Information: 14856 W COBALT ST 91342

Application / Permit
22014-20000-04481
Plan Check / Job No.
B22VN13544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Detached Garage conversion and addition to new ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/21/2022
Issuing Office
Current Status
CofO Issued on 2/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 HANS SANTIAGO
Corrections Issued 9/10/2022 HANS SANTIAGO
Plan Check Approved 10/10/2022 ANDREW SANTIAGO
Issued 10/21/2022 APPLICANT
CofO in Progress 2/6/2024 CHRISTOPHER ROJAS
Permit Finaled 2/23/2024 RUBEN SALAS
CofO Issued 2/23/2024 RUBEN SALAS
Permit Finaled 2/23/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/12/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/12/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/19/2022 COLIN LOREDO
Sewer availability Cleared 9/19/2022 COLIN LOREDO
Hydrant and Access approval Cleared 10/7/2022 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/6/2023 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 7/12/2023 Approved RAUL OLAGI
PLUMBING-Rough 7/12/2023 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Approved KEVIN BERBERYAN
Gas Test 8/29/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 8/29/2023 Corrections Issued KEVIN BERBERYAN
Sewer 8/29/2023 Approved KEVIN BERBERYAN
Wood Frame 8/29/2023 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 9/18/2023 Not Ready for Inspection KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 9/18/2023 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 9/21/2023 Approved KEVIN BERBERYAN
HVAC-Rough 9/21/2023 Approved KEVIN BERBERYAN
Insulation 9/21/2023 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 9/21/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/26/2023 Approved ROBERT GOLD
Green Building Rough 9/26/2023 Approved ROBERT GOLD
Insulation 9/26/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 9/26/2023 Partial Approval ROBERT GOLD
Underground Mechanical 9/26/2023 Approved ROBERT GOLD
Insulation 9/27/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 9/27/2023 Approved KEVIN BERBERYAN
Drywall Nailing 10/4/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/16/2023 Approved KEVIN BERBERYAN
Shower Pan 10/16/2023 Approved KEVIN BERBERYAN
Final 12/22/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 12/22/2023 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 12/22/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Final 2/2/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 2/2/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 2/2/2024 Approved CHRISTOPHER ROJAS