7432 N TOPEKA DR 91335
Certificate Information: 7432 N TOPEKA DR 91335
- Application / Permit
- 22014-20000-04479
- Plan Check / Job No.
- B22VN13534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage conversion to ADU with addition Per Ordinance and LAMC 12.22 A 33(c)&(d). All work per Engineer Design. After CfO is issued for ADU,the overall density is counted for permitted zone per LAMC 12.22 A33(h)(2).
- Permit Issued
- Issued on 2/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | ZAW HAN |
| Corrections Issued | 9/11/2022 | ZAW HAN |
| Plan Check Approved | 2/6/2023 | ZAW HAN |
| Issued | 2/7/2023 | APPLICANT |
| CofO in Progress | 9/18/2023 | JEFFREY BULL |
| Permit Finaled | 9/29/2023 | JOHN JANSON |
| CofO Issued | 9/29/2023 | JOHN JANSON |
| Permit Finaled | 9/29/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/23/2022 | MARTIN FRAGOSO |
| Construction near power lines | Cleared | 1/31/2023 | RIDWAN HARDY |
| Address approval | Cleared | 2/2/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 2/2/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 2/2/2023 | COLIN LOREDO |
| Hold | Cleared | 4/17/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/20/2023 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 4/18/2023 | Conditional Approval | JEFFREY BULL |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 4/21/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 4/27/2023 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 4/27/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | JEFFREY BULL |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| Insulation | 6/9/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 6/21/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/21/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 9/12/2023 | Corrections Issued | JEFFREY BULL |
| Final | 9/12/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/12/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 9/12/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 9/15/2023 | Approved | JEFFREY BULL |
| Final | 9/15/2023 | OK to Issue CofO | JEFFREY BULL |
| HVAC-Final | 9/15/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 9/15/2023 | Approved | JEFFREY BULL |
| Service/Power Release | 9/15/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 9/15/2023 | Approved | JEFFREY BULL |