10128 N ALDEA AVE 91325

Certificate Information: 10128 N ALDEA AVE 91325

Application / Permit
22014-20000-04470
Plan Check / Job No.
B22VN13526
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into ADU. Per State Law and GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 4/19/2023
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 ZAW HAN
Corrections Issued 9/10/2022 ZAW HAN
Applicant returned to address corrections 1/9/2023 ZAW HAN
Plan Check Approved 1/10/2023 ZAW HAN
Issued 4/19/2023 APPLICANT
CofO in Progress 10/2/2023 JAVIER RAMOS JR
Permit Finaled 12/21/2023 RUBEN SALAS
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/14/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 10/14/2022 MEGAN GODINEZ
Sewer availability Cleared 10/14/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/19/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 10/19/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 10/19/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 10/19/2022 MEGAN GODINEZ
Construction near power lines Cleared 12/17/2022 RIDWAN HARDY
Construction within easement Cleared 12/17/2022 RIDWAN HARDY

Contact Information

Contractor Gaga Builders Inc; Lic. No.: 1038675-B       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2023 Partial Approval JAVIER RAMOS JR
Sewer 5/16/2023 Approved JAVIER RAMOS JR
Underground Mechanical 5/16/2023 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 5/23/2023 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 5/24/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/20/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/20/2023 Corrections Issued JAVIER RAMOS JR
Green Building Rough 6/20/2023 Approved JAVIER RAMOS JR
HVAC-Rough 6/20/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 6/20/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/28/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 6/28/2023 Approved JAVIER RAMOS JR
HVAC-Rough 6/28/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/28/2023 Partial Approval JAVIER RAMOS JR
Drywall Nailing 7/31/2023 Partial Inspection JAVIER RAMOS JR
Insulation 7/31/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 7/31/2023 Approved JAVIER RAMOS JR
Shower Pan 7/31/2023 Approved JAVIER RAMOS JR
Final 9/26/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/26/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/26/2023 Approved JAVIER RAMOS JR
Final 10/2/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 10/2/2023 Approved JAVIER RAMOS JR