10556 N ENCINO AVE 91344

Certificate Information: 10556 N ENCINO AVE 91344

Application / Permit
22014-20000-04446
Plan Check / Job No.
B22VN13445
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 2/19/2024
Issuing Office
Current Status
CofO Issued on 1/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 MINA HABILI
Corrections Issued 11/27/2022 MINA HABILI
Applicant returned to address corrections 5/11/2023 MINA HABILI
Applicant returned to address corrections 8/1/2023 MINA HABILI
Applicant returned to address corrections 8/3/2023 MINA HABILI
Plan Check Approved 8/15/2023 MINA HABILI
Issued 2/19/2024 APPLICANT
CofO in Progress 1/6/2026 CHRISTOPHER ROJAS
Permit Finaled 1/10/2026 RUBEN SALAS
CofO Issued 1/10/2026 RUBEN SALAS
Permit Finaled 1/10/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/1/2023 ROMAN GUTIERREZ
Sewer availability Cleared 2/8/2023 ROMAN GUTIERREZ
Low Impact Development Cleared 3/23/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 3/30/2023 ROMAN GUTIERREZ

Contact Information

Contractor E - 1 Construction Inc; Lic. No.: 696414-B       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 4/4/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/15/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/15/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 5/22/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/26/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 7/26/2024 Approved MICHEL ABAJAN
Green Building Rough 7/26/2024 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 7/26/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 7/26/2024 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 8/27/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/11/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/11/2024 Approved JAVIER RAMOS JR
Wood Frame 9/11/2024 Approved JAVIER RAMOS JR
Insulation 9/18/2024 Partial Inspection MATTHEW NELSON
Drywall Nailing 9/27/2024 Approved JAVIER RAMOS JR
Insulation 9/27/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/15/2024 Approved MICHAEL CORTEZ
Final 2/5/2025 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 2/5/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/27/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 6/27/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 6/27/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 6/27/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 6/27/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Final 6/27/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Final 6/27/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 6/27/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 7/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 7/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 7/10/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 7/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 7/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Not Ready CHRISTOPHER ROJAS
ELECTRICAL-Final 7/15/2025 Approved CHRISTOPHER ROJAS
Final 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 7/15/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 7/15/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/6/2026 Approved CHRISTOPHER ROJAS
Final 1/6/2026 OK to Issue CofO CHRISTOPHER ROJAS
HVAC-Final 1/6/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/6/2026 Approved CHRISTOPHER ROJAS