8105 W APPERSON ST 91040
Certificate Information: 8105 W APPERSON ST 91040
- Application / Permit
- 22014-20000-04443
- Plan Check / Job No.
- B22VN13437
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition to existing single family residence
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | ZAW HAN |
| Corrections Issued | 9/9/2022 | ZAW HAN |
| Plan Check Approved | 10/27/2022 | ZAW HAN |
| Issued | 10/28/2022 | APPLICANT |
| CofO in Progress | 6/11/2024 | DAVID ANDERSON |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
| CofO Issued | 7/3/2024 | RUBEN SALAS |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/16/2022 | PATRICK MAGALLANES |
| Construction within easement | Cleared | 10/17/2022 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 10/17/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 10/18/2022 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 10/27/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 10/27/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 10/27/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Powell,, Gregory M; Lic. No.: C28099 | 9821 SHADOW ISLAND DR. SHADOW HILLS, CA 91040 |
| Architect | Powell,, Gregory M; Lic. No.: NA28099 | , |
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/30/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/10/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 10/10/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/10/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | DAVID ANDERSON |
| Gas Test | 10/24/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/24/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 11/7/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/7/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/5/2023 | Approved | MICHEL ABAJAN |
| Final | 5/31/2024 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 5/31/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 6/5/2024 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 6/5/2024 | Approved | DAVID ANDERSON |