11018 N BURNET AVE 91345

Certificate Information: 11018 N BURNET AVE 91345

Application / Permit
22014-20000-04434
Plan Check / Job No.
B22VN13428
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Interior remodel, addition to and conversion of the existing second unit (#11018) to an accessory dwelling unit per Ordinance and LAMC 12.22 A 33(c)&(d). All work per WFPP.
Permit Issued
Issued on 10/27/2022
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 ZAW HAN
Corrections Issued 9/9/2022 ZAW HAN
Plan Check Approved 10/23/2022 ZAW HAN
Issued 10/27/2022 APPLICANT
CofO in Progress 6/5/2023 JENNIFER RABUCHIN
CofO Issued 6/26/2023 MICHAEL SMITH
Permit Finaled 6/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/13/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/13/2022 COLIN LOREDO
Sewer availability Cleared 9/13/2022 COLIN LOREDO
Tenant Habitability Plan Cleared 10/4/2022 RICARDO BOHORQUEZ
Hydrant and Access approval Cleared 10/17/2022 MATTHEW CRAIG
Low Impact Development Cleared 10/19/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/19/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/1/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/1/2022 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 12/1/2022 Partial Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/5/2022 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/18/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/23/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 1/23/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 1/23/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/23/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/31/2023 Approved JENNIFER RABUCHIN
Green Building Rough 1/31/2023 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 1/31/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/31/2023 Approved JENNIFER RABUCHIN
Insulation 2/3/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 2/3/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 2/8/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/8/2023 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 2/17/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/1/2023 Approved JENNIFER RABUCHIN
Shower Pan 3/1/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/23/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/23/2023 Corrections Issued JENNIFER RABUCHIN
Final 5/23/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/23/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/23/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/23/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/31/2023 Approved JENNIFER RABUCHIN
Final 5/31/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/31/2023 Approved JENNIFER RABUCHIN
HVAC-Final 5/31/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/31/2023 Partial Approval JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved JENNIFER RABUCHIN
Final 6/6/2023 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 6/6/2023 Approved JENNIFER RABUCHIN