17250 W KNAPP ST 91325
Certificate Information: 17250 W KNAPP ST 91325
- Application / Permit
- 22014-20000-04423
- Plan Check / Job No.
- B22VN13409
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL FOR (E) SFD . RE-FRAME ROOF
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 9/8/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/6/2022 | APPLICANT |
| Plan Check Approved | 10/11/2022 | VARAND SARKISIAN |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 2/19/2025 | JAVIER RAMOS JR |
| Permit Finaled | 3/16/2025 | RUBEN SALAS |
| CofO Issued | 3/16/2025 | RUBEN SALAS |
| Permit Finaled | 3/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/16/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/2/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/13/2022 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 12/13/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/13/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/27/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/27/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 1/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/27/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/27/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/8/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/8/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/10/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/10/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 2/22/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/27/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 5/8/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/22/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/12/2024 | Partial Inspection | JAVIER RAMOS JR |
| Final | 9/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 9/12/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/12/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/18/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/18/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 2/18/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/18/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/18/2025 | Approved | JAVIER RAMOS JR |