16413 W NAPA ST 91343

Certificate Information: 16413 W NAPA ST 91343

Application / Permit
22014-20000-04333
Plan Check / Job No.
B22VN13112
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
5'-0"x7'-8",33'-3"x12'-6" IRREGULAR SHAPPED ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/12/2022
Issuing Office
Current Status
CofO Issued on 12/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 JESSE ARELLANO
Corrections Issued 9/2/2022 JESSE ARELLANO
Building Plans Picked Up 9/6/2022 APPLICANT
Plan Check Approved 9/12/2022 OMAR GARNICA
Issued 10/12/2022 APPLICANT
CofO in Progress 10/17/2024 RAUL OLAGI
CofO in Progress 10/21/2024 RAUL OLAGI
CofO in Progress 12/4/2024 RAUL OLAGI
Permit Finaled 12/14/2024 RUBEN SALAS
CofO Issued 12/14/2024 RUBEN SALAS
Permit Finaled 12/14/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/12/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/12/2022 CARLOS AGUILERA

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Valencia,, Byron Steve; Lic. No.: C87372 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 11/2/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 11/7/2022 Not Ready for Inspection RAUL OLAGI
Sewer 11/7/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 11/9/2022 Partial Approval RAUL OLAGI
Sewer 11/9/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 11/16/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved RAUL OLAGI
Green Building Rough 12/23/2022 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 12/23/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 1/4/2023 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 1/4/2023 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 1/4/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 1/27/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/27/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 1/27/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 1/27/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/6/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/6/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 2/6/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/6/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/13/2023 Approved RAUL OLAGI
Green Building Rough 2/13/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/13/2023 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/13/2023 Approved RAUL OLAGI
Insulation 2/14/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/14/2023 Partial Approval RAUL OLAGI
Drywall Nailing 2/16/2023 Approved RAUL OLAGI
Shower Pan 2/28/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 3/3/2023 Approved RAUL OLAGI
Wood Frame 3/17/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 3/20/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 3/20/2023 Conditional Approval ROBERT GOLD
Final 5/15/2023 Corrections Issued RAUL OLAGI
Green Building Final 5/15/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/15/2023 Approved RAUL OLAGI
Final 7/22/2024 Corrections Issued RAUL OLAGI
Final 10/17/2024 Corrections Issued RAUL OLAGI
Special/Order Compliance 10/21/2024 Corrections Issued RAUL OLAGI
Final 12/4/2024 OK to Issue CofO RAUL OLAGI