16413 W NAPA ST 91343
Certificate Information: 16413 W NAPA ST 91343
- Application / Permit
- 22014-20000-04333
- Plan Check / Job No.
- B22VN13112
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 5'-0"x7'-8",33'-3"x12'-6" IRREGULAR SHAPPED ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | JESSE ARELLANO |
| Corrections Issued | 9/2/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Plan Check Approved | 9/12/2022 | OMAR GARNICA |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 10/17/2024 | RAUL OLAGI |
| CofO in Progress | 10/21/2024 | RAUL OLAGI |
| CofO in Progress | 12/4/2024 | RAUL OLAGI |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| CofO Issued | 12/14/2024 | RUBEN SALAS |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/12/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/2/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/7/2022 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 11/7/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 11/9/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 11/9/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 11/16/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 12/23/2022 | Not Ready for Inspection | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 12/23/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/4/2023 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 1/4/2023 | Not Ready for Inspection | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 1/4/2023 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/6/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/6/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 2/6/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 2/6/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 2/13/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/13/2023 | Not Ready for Inspection | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 2/13/2023 | Approved | RAUL OLAGI |
| Insulation | 2/14/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 2/16/2023 | Approved | RAUL OLAGI |
| Shower Pan | 2/28/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/3/2023 | Approved | RAUL OLAGI |
| Wood Frame | 3/17/2023 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 3/20/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 3/20/2023 | Conditional Approval | ROBERT GOLD |
| Final | 5/15/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/15/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/15/2023 | Approved | RAUL OLAGI |
| Final | 7/22/2024 | Corrections Issued | RAUL OLAGI |
| Final | 10/17/2024 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 10/21/2024 | Corrections Issued | RAUL OLAGI |
| Final | 12/4/2024 | OK to Issue CofO | RAUL OLAGI |