7707 N WHITE OAK AVE 91335
Certificate Information: 7707 N WHITE OAK AVE 91335
- Application / Permit
- 22014-20000-04314
- Plan Check / Job No.
- B22VN13061
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 16' 4" X 11' RECREATION ROOM LOCATED IN FRONT PORTION OF (E) SFD. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/31/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/26/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/19/2022 | OMAR GARNICA |
| Plan Check Approved | 10/31/2022 | ANGELICA MARTINEZ |
| Issued | 10/31/2022 | APPLICANT |
| CofO in Progress | 2/28/2025 | JUAN ALVARADO |
| CofO Issued | 3/28/2025 | JOHN JANSON |
| Permit Finaled | 3/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 10/21/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2024 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 12/12/2024 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 12/16/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 1/8/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Special/Order Compliance | 1/15/2025 | Partial Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 1/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 1/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 1/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/29/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Insulation | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 2/10/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 2/28/2025 | Approved | JUAN ALVARADO |
| Final | 2/28/2025 | OK to Issue CofO | JUAN ALVARADO |
| Footing/Foundation/Slab | 2/28/2025 | Approved | JUAN ALVARADO |
| Green Building Final | 2/28/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 2/28/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 2/28/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 2/28/2025 | Approved | JUAN ALVARADO |