11154 W ARCHWOOD ST 91606
Certificate Information: 11154 W ARCHWOOD ST 91606
- Application / Permit
- 22014-20000-04312
- Plan Check / Job No.
- B22VN13056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND IRREGULAR SHAPED ADDITION TO (E) SFD. SPRINKLER NFPA 13D REQUIRED THROUGHOUT. ( SEE COMMENT )
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 1/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 9/3/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/9/2022 | APPLICANT |
| Applicant returned to address corrections | 4/30/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 5/13/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 6/17/2024 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 6/20/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 7/8/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/22/2024 | KAMYAR EMAMI |
| Plan Check Approved | 4/3/2025 | MOHAMMAD ESMAILI |
| Issued | 4/4/2025 | APPLICANT |
| CofO in Progress | 1/23/2026 | JOSE AVILA |
| CofO in Progress | 1/26/2026 | RAUL OLAGI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/9/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 10/20/2024 | TINA MIRANDA |
| Low Impact Development | Cleared | 3/4/2025 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/28/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 5/29/2025 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/3/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 6/3/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/3/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 6/17/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/2/2025 | Approved | MICHAEL CORTEZ |
| Final | 9/12/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 9/12/2025 | Approved | JOSE AVILA |
| Final | 11/4/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 11/4/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/4/2025 | Approved | JOSE AVILA |
| Final | 1/22/2026 | Not Ready for Inspection | JOSE AVILA |
| Special/Order Compliance | 1/26/2026 | Corrections Issued | JOSE AVILA |