10514 N PINEWOOD AVE 91042
Certificate Information: 10514 N PINEWOOD AVE 91042
- Application / Permit
- 22014-20000-04307
- Plan Check / Job No.
- B22VN13042
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 25'-9" x 18'-5" IRREGULAR SHAPED ADDITION AND REMODEL TO THE (E)SINGLE FAMILY DWELLING FOR A NEW DEN AND A LAUNDRY ROOM AND REMODEL KITCHEN.
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 7/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 9/1/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Plan Check Approved | 9/1/2023 | SARKIS HARABEDIAN |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 7/6/2026 | NICHOLAS TROWBRIDGE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/1/2022 | JEROME MAGAT PALMA |
| Low Impact Development | Cleared | 7/28/2023 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/21/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/19/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/20/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 3/26/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 3/27/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/23/2024 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 5/28/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/28/2024 | Corrections Issued | WILLIAM WREN |
| Insulation | 5/28/2024 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 5/28/2024 | Corrections Issued | WILLIAM WREN |
| Wood Frame | 5/28/2024 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | WILLIAM WREN |
| Deputy Drilled-In Anchors | 5/31/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 5/31/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/31/2024 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 5/31/2024 | Approved | WILLIAM WREN |
| Insulation | 6/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 6/7/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/7/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/4/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/5/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 10/10/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 10/10/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 10/30/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 10/30/2025 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 10/30/2025 | Approved | CRAIG DAVIS |
| Final | 12/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 7/2/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |