7539 N CLAYBECK AVE 91505

Certificate Information: 7539 N CLAYBECK AVE 91505

Application / Permit
22014-20000-04293
Plan Check / Job No.
B22VN13012
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'0"X18'0" ADDITION TO SFD
Permit Issued
Issued on 8/23/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 MARVEL DELACRUZ
Corrections Issued 9/15/2022 MARVEL DELACRUZ
Quality Review Completed 9/21/2022 OMID HEDAYAT
Building Plans Picked Up 9/26/2022 APPLICANT
Applicant returned to address corrections 8/10/2023 MARVEL DELACRUZ
Plan Check Approved 8/22/2023 MARVEL DELACRUZ
Issued 8/23/2023 APPLICANT
CofO in Progress 7/11/2025 DAVID ANDERSON
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/14/2022 CARLOS AGUILERA
Sewer availability Cleared 12/14/2022 CARLOS AGUILERA
ZA Case Cleared 3/9/2023 DANG NGUYEN
Hydrant and Access approval Cleared 3/30/2023 GILBERT URREA
Green Code Cleared 7/26/2023 MARVEL DELACRUZ
Low Impact Development Cleared 7/27/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/31/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/11/2023 Approved DAVID ANDERSON
PLUMBING-Rough 11/2/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 11/16/2023 Partial Approval DAVID ANDERSON
PLUMBING-Rough 1/29/2024 Approved DAVID ANDERSON
Insulation 2/1/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/20/2024 Approved DAVID ANDERSON
ELECTRICAL-Rough 6/20/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 7/1/2024 Approved DAVID ANDERSON
Green Building Rough 7/1/2024 Approved DAVID ANDERSON
HVAC-Rough 7/1/2024 Approved DAVID ANDERSON
Insulation 7/16/2024 Approved MATTHEW NELSON
Drywall Nailing 7/26/2024 Approved DAVID ANDERSON
Shower Pan 9/5/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/17/2024 Approved DAVID ANDERSON
Final 1/3/2025 Corrections Issued DAVID ANDERSON
Green Building Final 1/3/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 1/3/2025 Approved DAVID ANDERSON
Final 4/1/2025 Partial Approval JAVIER RAMOS JR
Green Building Final 4/1/2025 Approved JAVIER RAMOS JR
Final 7/11/2025 OK to Issue CofO DAVID ANDERSON