8424-8426 W HILLROSE ST 91040
Certificate Information: 8424-8426 W HILLROSE ST 91040
- Application / Permit
- 22014-20000-04273
- Plan Check / Job No.
- B22VN12943
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert existing 354 SF attached garage to an ADU with 25 SF Addition per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofO Issued on 4/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2022 | HANS SANTIAGO |
| Corrections Issued | 8/30/2022 | HANS SANTIAGO |
| Plan Check Approved | 9/22/2022 | ANDREW SANTIAGO |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 4/22/2024 | WILLIAM WREN |
| Permit Finaled | 4/24/2024 | RUBEN SALAS |
| CofO Issued | 4/24/2024 | RUBEN SALAS |
| Permit Finaled | 4/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 9/6/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 9/8/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 9/21/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2023 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 1/26/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 1/26/2023 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 1/26/2023 | Not Ready for Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 2/13/2023 | Conditional Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 2/21/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 2/27/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/27/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 6/26/2023 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 6/26/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 6/26/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 7/5/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/5/2023 | Approved | WILLIAM WREN |
| Insulation | 7/24/2023 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Partial Approval | WILLIAM WREN |
| Insulation | 8/3/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/15/2023 | Approved | WILLIAM WREN |
| Shower Pan | 8/28/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/30/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/21/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 2/2/2024 | Approved | MATTHEW NELSON |
| Final | 2/2/2024 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 2/2/2024 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 2/2/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 2/2/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/2/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/8/2024 | SGSOV Approved | WILLIAM WREN |
| Final | 2/13/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 3/19/2024 | Corrections Issued | WILLIAM WREN |
| Final | 3/27/2024 | OK to Issue CofO | WILLIAM WREN |