eplan* IRREGULAR SHAPE 41'-0" X 35'-2.5" AND 11'-0" X 11'-0" ADDITION TO SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ADDITION OF 20'-0" X 25'-6" ATTACHED STORAGE, 41'-0" X 20'-0" COVERED PATIO, 16'-0" X 6'-0" COVERED ENTRY AND INTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING - ALL WORK PER DESIGN - FIRE SPRINKLERED REQUIRED THROUGH OUT
Permit Issued
Issued on 1/11/2023
Issuing Office
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 8/31/2022 DANIEL SANJUAN
Corrections Issued 9/1/2022 DANIEL SANJUAN
Applicant returned to address corrections 12/13/2022 JOSEPH RAFOLS
Plan Check Approved 1/6/2023 DANIEL ABRAMYAN
Plan Check Approved 1/11/2023 DANIEL ABRAMYAN
Issued 1/11/2023 APPLICANT
CofO in Progress 8/2/2024 SEAN WIRCH
Permit Finaled 8/26/2024 JOHN JANSON
CofO Issued 8/26/2024 JOHN JANSON
Permit Finaled 8/26/2024 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 9/2/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/6/2022 MEGAN GODINEZ
Low Impact Development Cleared 11/2/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 12/1/2022 MEGAN GODINEZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/25/2023 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 1/26/2023 Corrections Issued JON MCHUGH
Sewer 1/26/2023 Approved JON MCHUGH
Excavation/Setback/Form/Re-Bar 1/27/2023 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/7/2023 Approved JON MCHUGH
Footing/Foundation/Slab 2/7/2023 Approved JON MCHUGH
Wood Frame 2/7/2023 Not Ready for Inspection JON MCHUGH
Deputy Drilled-In Anchors 2/13/2023 Conditional Approval JON MCHUGH
PLUMBING-Rough 3/6/2023 Partial Approval SEAN HAUPT
Special/Order Compliance 3/6/2023 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval JON MCHUGH
Green Building Rough 4/10/2023 Not Ready for Inspection JON MCHUGH
Deputy Wood Construction 4/19/2023 Conditional Approval JON MCHUGH
ELECTRICAL-Rough 4/25/2023 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Approved JON MCHUGH
HVAC-Rough 4/27/2023 Corrections Issued JON MCHUGH
HVAC-Rough 5/2/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 5/2/2023 Approved JUSTIN HAWLEY
Pre-Inspection 5/2/2023 Partial Inspection JOHN KIDWELL
Interior/Exterior Lathing 5/4/2023 Not Ready for Inspection JON MCHUGH
Wood Frame 5/4/2023 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 5/8/2023 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 5/11/2023 Approved JEFFREY BULL
Green Building Rough 5/11/2023 Approved JEFFREY BULL
Insulation 5/11/2023 Approved JEFFREY BULL
Shower Pan 5/11/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 5/12/2023 Approved ALEXANDER HANDY
Drywall Nailing 5/24/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Final 7/31/2024 Approved SEAN WIRCH
Final 7/31/2024 OK to Issue CofO SEAN WIRCH
Green Building Final 7/31/2024 Approved SEAN WIRCH
HVAC-Final 7/31/2024 Approved SEAN WIRCH
PLUMBING-Final 7/31/2024 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved SEAN WIRCH
Service/Power Release 7/31/2024 Approved SEAN WIRCH
Smoke Detectors 7/31/2024 Approved SEAN WIRCH