6922 N WISH AVE 91406
Certificate Information: 6922 N WISH AVE 91406
- Application / Permit
- 22014-20000-04261
- Plan Check / Job No.
- B22VN12904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan* IRREGULAR SHAPE 41'-0" X 35'-2.5" AND 11'-0" X 11'-0" ADDITION TO SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ADDITION OF 20'-0" X 25'-6" ATTACHED STORAGE, 41'-0" X 20'-0" COVERED PATIO, 16'-0" X 6'-0" COVERED ENTRY AND INTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING - ALL WORK PER DESIGN - FIRE SPRINKLERED REQUIRED THROUGH OUT
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | DANIEL SANJUAN |
| Corrections Issued | 9/1/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 12/13/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 1/6/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/11/2023 | DANIEL ABRAMYAN |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 8/2/2024 | SEAN WIRCH |
| Permit Finaled | 8/26/2024 | JOHN JANSON |
| CofO Issued | 8/26/2024 | JOHN JANSON |
| Permit Finaled | 8/26/2024 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 11/2/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/1/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 12/1/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 12/1/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 12/1/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 1/26/2023 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Partial Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 2/7/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 2/7/2023 | Approved | JON MCHUGH |
| Wood Frame | 2/7/2023 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 2/13/2023 | Conditional Approval | JON MCHUGH |
| PLUMBING-Rough | 3/6/2023 | Partial Approval | SEAN HAUPT |
| Special/Order Compliance | 3/6/2023 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | JON MCHUGH |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Deputy Wood Construction | 4/19/2023 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 4/25/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 4/27/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 5/2/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 5/2/2023 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 5/2/2023 | Partial Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/4/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 5/4/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 5/8/2023 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 5/11/2023 | Approved | JEFFREY BULL |
| Insulation | 5/11/2023 | Approved | JEFFREY BULL |
| Shower Pan | 5/11/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/12/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/24/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/31/2024 | Approved | SEAN WIRCH |
| Final | 7/31/2024 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 7/31/2024 | Approved | SEAN WIRCH |
| HVAC-Final | 7/31/2024 | Approved | SEAN WIRCH |
| PLUMBING-Final | 7/31/2024 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 7/31/2024 | Approved | SEAN WIRCH |
| Smoke Detectors | 7/31/2024 | Approved | SEAN WIRCH |