9048 N TERHUNE AVE 91352
Certificate Information: 9048 N TERHUNE AVE 91352
- Application / Permit
- 22014-20000-04256
- Plan Check / Job No.
- B22VN12896
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW (19'-6"x17'-0"), 304 SQFT RECREATION ROOM ATTACHED THE (E) DETACHED GARAGE
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Current Status
- CofO Issued on 11/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | PETER MOSESIAN |
| Corrections Issued | 8/27/2022 | PETER MOSESIAN |
| Quality Review Completed | 8/31/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Plan Check Approved | 8/1/2023 | PETER MOSESIAN |
| Issued | 8/1/2023 | APPLICANT |
| CofO in Progress | 10/1/2024 | DAVID ANDERSON |
| Permit Finaled | 11/23/2024 | DANIEL ORRANTE |
| CofO Issued | 11/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/20/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/8/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 2/22/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 7/7/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2023 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 11/30/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 12/7/2023 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 1/10/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 1/12/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 1/30/2024 | Approved | DAVID ANDERSON |
| Sewer | 1/30/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 1/30/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/9/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 2/9/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/20/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/4/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/4/2024 | Approved | DAVID ANDERSON |
| Insulation | 4/4/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/10/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 5/23/2024 | Approved | DAVID ANDERSON |
| Final | 7/8/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/8/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 7/8/2024 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 7/8/2024 | Approved | DAVID ANDERSON |
| Final | 9/19/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 9/19/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/30/2024 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 9/30/2024 | Approved | DAVID ANDERSON |