10144 N SALOMA AVE 91345

Certificate Information: 10144 N SALOMA AVE 91345

Application / Permit
22014-20000-04246
Plan Check / Job No.
B22VN12871
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADD 422 ft² TO ADD BEDROOM BATHROOM REMODEL EXISTING BATHROOM & BEDROOM REPLACE WINDOW AT BEDROOM
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 SUNMIN LEE
Corrections Issued 8/30/2022 SUNMIN LEE
Applicant returned to address corrections 9/2/2022 SUNMIN LEE
Plan Check Approved 9/20/2022 SUNMIN LEE
No Progress 10/26/2022 SUNMIN LEE
Plan Check Approved 11/3/2022 SUNMIN LEE
Issued 2/9/2023 APPLICANT
CofO in Progress 10/16/2023 RYAN SALAZAR
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/30/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/31/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/31/2022 ROMAN GUTIERREZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Oag; Lic. No.: 1101018-B 9712 LIVE OAK AVE      TEMPLE CITY, CA 91780

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/10/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 2/13/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/17/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 2/17/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 2/17/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/6/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/6/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/6/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 3/6/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 3/6/2023 Approved JENNIFER RABUCHIN
Wood Frame 3/6/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/7/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 3/7/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/7/2023 Approved JENNIFER RABUCHIN
Insulation 3/9/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 3/13/2023 Approved WILLIAM WREN
Green Building Rough 3/13/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 3/20/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Final 8/7/2023 Corrections Issued JENNIFER RABUCHIN
Final 8/7/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 8/7/2023 Approved JENNIFER RABUCHIN
Green Building Final 8/7/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 8/7/2023 Approved JENNIFER RABUCHIN
Final 9/29/2023 Partial Approval RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved RYAN SALAZAR
Structural Steel Frame 9/29/2023 Approved RYAN SALAZAR
Final 10/17/2023 OK to Issue CofO RYAN SALAZAR