545 N FULLER AVE 90036

Certificate Information: 545 N FULLER AVE 90036

Application / Permit
22014-20000-04235
Plan Check / Job No.
B22VN12818
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 13' 10" X 17' 11" HABITABLE SPACE ADDITION AND 17' 11" X 6' 6" PATIO COVER ADDITION TO THE (E) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/24/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/22/2022 OMAR GARNICA
Corrections Issued 8/22/2022 OMAR GARNICA
Applicant returned to address corrections 9/20/2022 GURUNATH NESARAJAH
Plan Check Approved 10/24/2022 ALEC MOUSAKHANIAN
Issued 10/24/2022 APPLICANT
CofO in Progress 6/12/2023 LILIANA PORTILLO
Permit Finaled 6/15/2023 DEROLD HAUFF
CofO Issued 6/15/2023 DEROLD HAUFF
Permit Finaled 6/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/24/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 8/26/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/23/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 11/28/2022 Approved MICHAEL LEWIS
METHANE-Barrier 11/28/2022 Approved MICHAEL LEWIS
METHANE-Subgrade 11/28/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 1/4/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Approved MICHAEL LEWIS
METHANE-Rough 1/4/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/22/2023 Partial Approval MICHAEL LEWIS
Green Building Rough 2/22/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/22/2023 Approved MICHAEL LEWIS
Insulation 2/27/2023 Approved MICHAEL LEWIS
Drywall Nailing 3/3/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/26/2023 Approved LILIANA PORTILLO
Final 5/26/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 5/26/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/26/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/9/2023 Approved LILIANA PORTILLO
Final 6/9/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 6/9/2023 Approved LILIANA PORTILLO
PLUMBING-Final 6/9/2023 Approved LILIANA PORTILLO