1367 W YOSEMITE DR 90041

Certificate Information: 1367 W YOSEMITE DR 90041

Application / Permit
22014-20000-04226
Plan Check / Job No.
B22VN12795
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
CONVERT THE DETACHED CARPORT TO A GARAGE AND AN ADDITION TO CREATE A 22.5' x 24.5' GARAGE.
Permit Issued
Issued on 10/11/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/3/2022 LUIS RINCON
Corrections Issued 9/4/2022 LUIS RINCON
Building Plans Picked Up 9/8/2022 APPLICANT
Plan Check Approved 9/30/2022 LUIS RINCON
Issued 10/11/2022 APPLICANT
CofO in Progress 3/6/2023 CRAIG VAUGHAN
Permit Finaled 4/6/2023 DEROLD HAUFF
CofO Issued 4/6/2023 DEROLD HAUFF
Permit Finaled 4/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 9/19/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 9/19/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 9/20/2022 AMAAN MALIK

Contact Information

Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/1/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/7/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 11/18/2022 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 11/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/30/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/25/2023 Approved CRAIG VAUGHAN
Drywall Nailing 1/25/2023 Approved CRAIG VAUGHAN
Final 1/25/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/25/2023 Approved CRAIG VAUGHAN
Green Building Rough 1/25/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/25/2023 Approved CRAIG VAUGHAN
Final 2/3/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 3/3/2023 Approved CRAIG VAUGHAN
Final 3/3/2023 OK to Issue CofO CRAIG VAUGHAN