11206 N DE GARMO AVE 91331
Certificate Information: 11206 N DE GARMO AVE 91331
- Application / Permit
- 22014-20000-04220
- Plan Check / Job No.
- B22VN12782
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING RECREATION ROOM AND STORAGE INTO ADU ADU CHECKED PER GCS65852.2(E)(1)(A)
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | SUNMIN LEE |
| Corrections Issued | 8/30/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 9/28/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 10/24/2022 | SUNMIN LEE |
| Plan Check Approved | 12/4/2022 | JOE VO |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 3/17/2023 | MICHEL ABAJAN |
| Permit Finaled | 3/20/2023 | RONALD MYRICK |
| CofO Issued | 3/20/2023 | RONALD MYRICK |
| Permit Finaled | 3/20/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 9/1/2022 | MIGUEL GAMBOA |
| Address approval | Cleared | 9/8/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/8/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 9/27/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/30/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 12/30/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/30/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 12/30/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/12/2023 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 1/12/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 1/12/2023 | Approved | MICHEL ABAJAN |
| Insulation | 1/25/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/25/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/2/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/10/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 3/10/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 3/10/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/10/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 3/10/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/17/2023 | Approved | MICHEL ABAJAN |
| Final | 3/17/2023 | OK to Issue CofO | MICHEL ABAJAN |