915-915 1/2 E 78TH ST 90001
Certificate Information: 915-915 1/2 E 78TH ST 90001
- Application / Permit
- 22014-20000-04204
- Plan Check / Job No.
- B22VN12697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' 6" X 21' 11" IRR.-SHAPE ADDITION OF ACCESSORY DWELLING UNIT TO EXISTING SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c) AND (e) - ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- Issued on 5/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 9/3/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 2/27/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/29/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/7/2023 | GURUNATH NESARAJAH |
| Issued | 5/9/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/25/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 2/15/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/24/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christenson,, Paul Scott; Lic. No.: C57182 | 3529 COASTVIEW CT CARLSBAD, CA 92010 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2023 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/30/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/30/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 7/20/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/4/2023 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 8/4/2023 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/15/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 8/15/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/15/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/15/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 12/15/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/29/2023 | Partial Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/29/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 12/29/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/29/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/15/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/6/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/9/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 5/9/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Insulation | 6/7/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/14/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/14/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/27/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 9/27/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/27/2024 | Approved | MICHAEL LEWIS |
| HVAC-Final | 9/27/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 9/27/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 9/27/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 9/27/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 11/8/2024 | Partial Inspection | MICHAEL LEWIS |
| Final | 11/8/2024 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Final | 11/8/2024 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 11/8/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 11/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 11/8/2024 | Approved | MICHAEL LEWIS |
| Final | 3/7/2025 | Partial Approval | JOHN QUINTANILLA |
| Service/Power Release | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/2/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 3/26/2026 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 5/29/2026 | Corrections Issued | JOHN QUINTANILLA |