2717 E PEPPER AVE 90065

Certificate Information: 2717 E PEPPER AVE 90065

Application / Permit
22014-20000-04181
Plan Check / Job No.
B22VN12648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
30' X 8' 6" ADDITION TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 ARTIN ZARUKIAN
Corrections Issued 8/30/2022 ARTIN ZARUKIAN
Building Plans Picked Up 9/1/2022 APPLICANT
Applicant returned to address corrections 10/7/2022 MOHAMMAD ESMAILI
Plan Check Approved 1/18/2023 GURUNATH NESARAJAH
Issued 1/18/2023 APPLICANT
CofO in Progress 5/15/2023 OSVALDO PARAMO
CofO in Progress 5/15/2023 OSVALDO PARAMO
Permit Finaled 6/8/2023 DEROLD HAUFF
CofO Issued 6/8/2023 DEROLD HAUFF
Permit Finaled 6/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 10/14/2022 PRISCILLA RUIZ
ZI Cleared 10/18/2022 ASHLEY RODARTE
Grading Pre-Inspection Cleared 10/19/2022 KIRK LINKLATER
Address approval Cleared 10/20/2022 CINDY QI
Roof/Waste drainage to street Cleared 10/20/2022 CINDY QI
Permit Cleared 10/24/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 10/31/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 11/30/2022 CHRISTOPHER ROCHA
ZI Cleared 12/5/2022 NASHYA JENSEN
Construction near power lines Cleared 1/11/2023 RIDWAN HARDY

Contact Information

Contractor The New Beginning Construction Company; Lic. No.: 848904-B 3837 E COCHRAN STREET      SIMI VALLEY, CA 93063
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2023 Corrections Issued OSVALDO PARAMO
Sewer 1/31/2023 Partial Approval OSVALDO PARAMO
Underground Mechanical 1/31/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 2/9/2023 Approved BRIAN SULLIVAN
Underground Mechanical 2/9/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/6/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Approved OSVALDO PARAMO
HVAC-Rough 3/6/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 3/6/2023 Approved OSVALDO PARAMO
Wood Frame 3/6/2023 Corrections Issued OSVALDO PARAMO
Interior/Exterior Lathing 3/16/2023 Partial Approval RICHARD DOCKUS
Shower Pan 3/16/2023 Approved RICHARD DOCKUS
Wood Frame 3/16/2023 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 3/21/2023 Approved OSVALDO PARAMO
Green Building Rough 3/21/2023 Approved OSVALDO PARAMO
Insulation 3/21/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/21/2023 Approved OSVALDO PARAMO
Wood Frame 3/21/2023 Approved OSVALDO PARAMO
Drywall Nailing 3/28/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/26/2023 Corrections Issued OSVALDO PARAMO
Gas Test 4/26/2023 Approved OSVALDO PARAMO
HVAC-Final 4/26/2023 Approved OSVALDO PARAMO
PLUMBING-Final 4/26/2023 Approved OSVALDO PARAMO
Service/Power Release 4/26/2023 Not Ready for Inspection OSVALDO PARAMO
Final 5/10/2023 Conditional Approval OSVALDO PARAMO
Green Building Final 5/10/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/10/2023 Approved OSVALDO PARAMO
Final 5/15/2023 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 5/15/2023 Approved OSVALDO PARAMO