2717 E PEPPER AVE 90065
Certificate Information: 2717 E PEPPER AVE 90065
- Application / Permit
- 22014-20000-04181
- Plan Check / Job No.
- B22VN12648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 30' X 8' 6" ADDITION TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 8/30/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Applicant returned to address corrections | 10/7/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/18/2023 | GURUNATH NESARAJAH |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 5/15/2023 | OSVALDO PARAMO |
| CofO in Progress | 5/15/2023 | OSVALDO PARAMO |
| Permit Finaled | 6/8/2023 | DEROLD HAUFF |
| CofO Issued | 6/8/2023 | DEROLD HAUFF |
| Permit Finaled | 6/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 10/14/2022 | PRISCILLA RUIZ |
| ZI | Cleared | 10/18/2022 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 10/19/2022 | KIRK LINKLATER |
| Address approval | Cleared | 10/20/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | CINDY QI |
| Permit | Cleared | 10/24/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/30/2022 | CHRISTOPHER ROCHA |
| ZI | Cleared | 12/5/2022 | NASHYA JENSEN |
| Construction near power lines | Cleared | 1/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | The New Beginning Construction Company; Lic. No.: 848904-B | 3837 E COCHRAN STREET SIMI VALLEY, CA 93063 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2023 | Corrections Issued | OSVALDO PARAMO |
| Sewer | 1/31/2023 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 1/31/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/9/2023 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 2/9/2023 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/6/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/6/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/6/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/6/2023 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/16/2023 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 3/16/2023 | Approved | RICHARD DOCKUS |
| Wood Frame | 3/16/2023 | Conditional Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/21/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 3/21/2023 | Approved | OSVALDO PARAMO |
| Insulation | 3/21/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/21/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/21/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/28/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/26/2023 | Corrections Issued | OSVALDO PARAMO |
| Gas Test | 4/26/2023 | Approved | OSVALDO PARAMO |
| HVAC-Final | 4/26/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 4/26/2023 | Approved | OSVALDO PARAMO |
| Service/Power Release | 4/26/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 5/10/2023 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 5/10/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/10/2023 | Approved | OSVALDO PARAMO |
| Final | 5/15/2023 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 5/15/2023 | Approved | OSVALDO PARAMO |