8501 N TERHUNE AVE 91352
Certificate Information: 8501 N TERHUNE AVE 91352
- Application / Permit
- 22014-20000-04179
- Plan Check / Job No.
- B22VN12636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'-6" X 26'-3" ADDITION AND REMODEL TO ADD ONE NEW BEDROOM AND ONE NEW BATHROOM
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | LUIS RINCON |
| Corrections Issued | 8/30/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/7/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | JEROME MAGAT PALMA |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 10/18/2023 | CHRISTOPHER ROJAS |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
| CofO Issued | 5/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/8/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/30/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/30/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/30/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 1/30/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/30/2023 | Approved | DAVID ANDERSON |
| Smoke Detectors | 1/30/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 2/1/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/3/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/7/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 3/7/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 3/10/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/12/2023 | Approved | DAVID ANDERSON |
| Insulation | 4/12/2023 | Approved | DAVID ANDERSON |
| Final | 10/16/2023 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 10/16/2023 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/16/2023 | Approved | CHRISTOPHER ROJAS |