7791 N PEACHTREE AVE 91402

Certificate Information: 7791 N PEACHTREE AVE 91402

Application / Permit
22014-20000-04174
Plan Check / Job No.
B22VN12626
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* ADDITION (280 SF) TO (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE. ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 8/25/2022
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 VIVIAN LAO
Corrections Issued 8/19/2022 VIVIAN LAO
Plan Check Approved 8/25/2022 VIVIAN LAO
Issued 8/25/2022 APPLICANT
CofO in Progress 6/20/2024 VINCENT HANLEY
Permit Finaled 7/3/2024 RUBEN SALAS
CofO Issued 7/3/2024 RUBEN SALAS
Permit Finaled 7/3/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/22/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/22/2022 COLIN LOREDO
Sewer availability Cleared 8/22/2022 VIVIAN LAO

Contact Information

Architect Hanna,, Remon; Lic. No.: NA36271       ,
Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/19/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 9/27/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 9/27/2022 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 10/6/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 10/6/2022 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 10/17/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 10/17/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 12/23/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 12/23/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 12/23/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 1/4/2023 Approved GREGG CUMMINGS
Green Building Rough 1/4/2023 Approved GREGG CUMMINGS
Insulation 1/4/2023 Partial Approval GREGG CUMMINGS
Insulation 1/11/2023 Approved WILLIAM WREN
Drywall Nailing 1/23/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/23/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/25/2023 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 4/29/2024 Approved KIRK SANDERS
Final 4/29/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/29/2024 Approved KIRK SANDERS
Green Building Final 4/29/2024 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 4/29/2024 Approved KIRK SANDERS
ELECTRICAL-Final 6/20/2024 Approved VINCENT HANLEY
Final 6/20/2024 OK to Issue CofO VINCENT HANLEY
Green Building Final 6/20/2024 Approved VINCENT HANLEY
HVAC-Final 6/20/2024 Approved VINCENT HANLEY
PLUMBING-Final 6/20/2024 Approved VINCENT HANLEY