14420 W JUDD ST 91331

Certificate Information: 14420 W JUDD ST 91331

Application / Permit
22014-20000-04168
Plan Check / Job No.
B22VN12613
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
18.5' x 40' ADDITION TO GARAGE AND CONVERSION TO ADU
Permit Issued
Issued on 1/18/2023
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/24/2022 SAMUEL GONZALEZ
Corrections Issued 8/24/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 12/22/2022 SAMUEL GONZALEZ
Plan Check Approved 12/29/2022 HERNAN ARREOLA
Issued 1/18/2023 APPLICANT
CofO in Progress 12/21/2023 ROBERT GOLD
Permit Finaled 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/20/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/20/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/21/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 9/21/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/2/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2023 Partial Approval JENNIFER RABUCHIN
Sewer 3/28/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 3/28/2023 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/7/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/19/2023 Approved JENNIFER RABUCHIN
METHANE-Barrier 4/19/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 4/19/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/7/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/7/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Approved JENNIFER RABUCHIN
Gas Test 7/7/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/7/2023 Corrections Issued JENNIFER RABUCHIN
METHANE-Rough 7/7/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/7/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 7/7/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 7/20/2023 Partial Approval JENNIFER RABUCHIN
Insulation 7/27/2023 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 8/9/2023 Approved MATTHEW NELSON
Shower Pan 8/9/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/29/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/18/2023 Corrections Issued JENNIFER RABUCHIN
Final 10/18/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 10/18/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/18/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 10/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/18/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/24/2023 Approved JENNIFER RABUCHIN
Gas Test 10/24/2023 Approved JENNIFER RABUCHIN
Green Building Final 10/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 10/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/24/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/24/2023 Approved JENNIFER RABUCHIN
Final 10/27/2023 OK to Issue CofO JENNIFER RABUCHIN