14420 W JUDD ST 91331
Certificate Information: 14420 W JUDD ST 91331
- Application / Permit
- 22014-20000-04168
- Plan Check / Job No.
- B22VN12613
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18.5' x 40' ADDITION TO GARAGE AND CONVERSION TO ADU
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 8/24/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 12/22/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 12/29/2022 | HERNAN ARREOLA |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 12/21/2023 | ROBERT GOLD |
| Permit Finaled | 12/29/2023 | RUBEN SALAS |
| Permit Finaled | 12/29/2023 | RUBEN SALAS |
| CofO Issued | 12/29/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/21/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 12/2/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/28/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 3/28/2023 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 3/28/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/7/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 7/7/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/7/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Rough | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/7/2023 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 8/9/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 8/9/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/29/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 10/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 10/18/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/27/2023 | OK to Issue CofO | JENNIFER RABUCHIN |