6542 N VARNA AVE 91401

Certificate Information: 6542 N VARNA AVE 91401

Application / Permit
22014-20000-04163
Plan Check / Job No.
B22VN12603
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE SINGLE FAMILY DWELLING EXCEPT FOR (10'-0") WALL ON SOUTH PL AND BUILD NEW (40'-2"x87'-3"), 2069 SQFT SINGLE FAMILY DWELLING W/ATTACHED OPEN TRELLIS (21'-3"x16'-0") IN THE (E) SFD FOOTPRINT W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 PETER MOSESIAN
Corrections Issued 8/27/2022 PETER MOSESIAN
Quality Review Completed 8/31/2022 OMID HEDAYAT
Building Plans Picked Up 8/31/2022 APPLICANT
Plan Check Approved 9/14/2022 PETER MOSESIAN
Issued 9/14/2022 APPLICANT
CofO in Progress 7/19/2023 KIRK SANDERS
CofO Issued 10/23/2023 RUBEN SALAS
Permit Finaled 10/23/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/6/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/12/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/21/2022 Partial Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 10/24/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 10/24/2022 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 11/17/2022 Approved CALEB MEISTER
Insulation 11/17/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 11/17/2022 Partial Approval CALEB MEISTER
Insulation 11/22/2022 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 1/11/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 1/11/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 1/11/2023 Approved RAUL OLAGI
Shower Pan 1/11/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval MICHEL ABAJAN
HVAC-Rough 1/19/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/2/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 2/2/2023 Corrections Issued JUAN VALENZUELA
Green Building Rough 2/2/2023 Corrections Issued JUAN VALENZUELA
Verify Sprinkler Sign Off 2/2/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 2/10/2023 Approved JUAN VALENZUELA
ELECTRICAL-Rough 2/10/2023 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Approved JUAN VALENZUELA
Green Building Rough 2/10/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/10/2023 Partial Approval JUAN VALENZUELA
Insulation 2/21/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/21/2023 Approved MISAEL ESPARZA
Drywall Nailing 3/1/2023 Approved KIRK SANDERS
ELECTRICAL-Final 7/5/2023 Corrections Issued KIRK SANDERS
Final 7/5/2023 Corrections Issued KIRK SANDERS
Gas Test 7/5/2023 Approved KIRK SANDERS
HVAC-Final 7/5/2023 Approved KIRK SANDERS
PLUMBING-Final 7/5/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 7/17/2023 Approved KIRK SANDERS
Final 7/17/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 7/17/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/17/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 7/17/2023 Approved KIRK SANDERS
Smoke Detectors 7/17/2023 Approved KIRK SANDERS