12216 W HESBY ST 91607

Certificate Information: 12216 W HESBY ST 91607

Application / Permit
22014-20000-04152
Plan Check / Job No.
B22VN12566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ENTIRE GARAGE EXCEPT 20LF EAST WALL & 18LF NORTH/SOUTH WALL AND ADD (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ RECREATION ROOM & HALF BATH ABOVE
Permit Issued
Issued on 8/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 NILOOFAR MEHRAIN
Corrections Issued 8/30/2022 NILOOFAR MEHRAIN
Quality Review Completed 9/1/2022 STEVEN KIM
Building Plans Picked Up 9/1/2022 APPLICANT
Applicant returned to address corrections 1/5/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/21/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/7/2023 NILOOFAR MEHRAIN
Plan Check Approved 4/4/2023 NILOOFAR MEHRAIN
Issued 8/14/2023 APPLICANT
CofO in Progress 5/2/2025 GAREN HAYRAPETYAN
Permit Finaled 5/8/2025 RUBEN SALAS
CofO Issued 5/8/2025 RUBEN SALAS
Permit Finaled 5/8/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/10/2022 RIDWAN HARDY
Construction within easement Cleared 12/10/2022 RIDWAN HARDY
Address approval Cleared 12/14/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 1/9/2023 RYAN KIM
Sewer availability Cleared 1/9/2023 RYAN KIM
Specific Plan Cleared 1/11/2023 CHRISTIAN PEARSON
ZI Cleared 1/11/2023 CHRISTIAN PEARSON
Hydrant and Access approval Cleared 1/14/2023 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 1/30/2023 RYAN KIM

Contact Information

Contractor El Design Inc; Lic. No.: 1090237-B 3620 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2023 Conditional Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 8/28/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 8/28/2023 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 9/21/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 11/2/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 11/20/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 11/20/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 11/20/2023 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 11/22/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/22/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/22/2023 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/22/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/30/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 11/30/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Approved KIRK SANDERS
HVAC-Rough 11/30/2023 Approved KIRK SANDERS
PLUMBING-Rough 11/30/2023 Approved KIRK SANDERS
Wood Frame 12/5/2023 Approved KIRK SANDERS
Insulation 12/11/2023 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 12/11/2023 Corrections Issued DAVID MATSON
Insulation 12/13/2023 Approved MISAEL ESPARZA
Drywall Nailing 12/28/2023 Approved CRAIG DAVIS
Interior/Exterior Lathing 12/28/2023 Approved CRAIG DAVIS
Shower Pan 12/28/2023 Corrections Issued CRAIG DAVIS
Underground Mechanical 12/29/2023 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 2/14/2024 Approved KIRK SANDERS
Shower Pan 2/14/2024 Approved KIRK SANDERS
Service/Power Release 7/25/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 8/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Final 2/26/2025 Approved OGANES TARAKHCHYAN
Final 2/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 2/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 2/26/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/26/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 2/26/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 2/26/2025 Approved OGANES TARAKHCHYAN
Final 4/22/2025 Partial Approval OGANES TARAKHCHYAN
Green Building Final 4/22/2025 Approved OGANES TARAKHCHYAN
Final 5/2/2025 OK to Issue CofO GAREN HAYRAPETYAN