7466 N CLEON AVE 91352
Certificate Information: 7466 N CLEON AVE 91352
- Application / Permit
- 22014-20000-04135
- Plan Check / Job No.
- B22VN12521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU ADDITION TO (E) GARAGE PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g), GARAGE TO REMAIN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | SERGIO MUNIZ |
| Corrections Issued | 8/29/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Plan Check Approved | 2/9/2023 | LUISANGEL VALENZUELA |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | JOHN HAYES |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/2/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/7/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/1/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/2/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 5/17/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/8/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 6/15/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/10/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 10/10/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/10/2023 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 10/10/2023 | Corrections Issued | JOHN HAYES |
| Wood Frame | 10/10/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/19/2023 | Approved | JOHN HAYES |
| Green Building Rough | 10/19/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/19/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/8/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/8/2023 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/8/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | JOHN HAYES |
| Green Building Rough | 11/15/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/15/2023 | Approved | JOHN HAYES |
| Insulation | 11/27/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/8/2023 | Approved | JUAN VALENZUELA |
| Shower Pan | 12/12/2023 | Approved | ROBERT GOLD |
| Final | 3/21/2024 | Corrections Issued | JOHN COLEMAN |
| Final | 3/22/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/22/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 3/22/2024 | Approved | JOHN HAYES |
| Final | 4/1/2024 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | JOHN HAYES |