7927 N FALLBROOK AVE 1-3 91304
Certificate Information: 7927 N FALLBROOK AVE 1-3 91304
- Application / Permit
- 22014-20000-04131
- Plan Check / Job No.
- B22VN12518
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 20' X 20'-9" ATTACHED GARAGE TO NEW JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22; ADD 27' X 26' ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Valley
- Current Status
- Issued on 6/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/30/2022 | SELLA BENYAMIN |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Applicant returned to address corrections | 5/9/2023 | SELLA BENYAMIN |
| Plan Check Approved | 6/15/2023 | SELLA BENYAMIN |
| Issued | 6/20/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/23/2023 | MARTIN FRAGOSO |
| Address approval | Cleared | 4/18/2023 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 4/18/2023 | JOHN LIN |
| Sewer availability | Cleared | 4/18/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/5/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 3/5/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 4/23/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 4/23/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 6/6/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Sewer | 6/26/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 6/26/2024 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/11/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/7/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/14/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/27/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 11/27/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/27/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 12/12/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 5/12/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 5/12/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 5/12/2025 | Corrections Issued | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/3/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/9/2026 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Rough | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 4/6/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 4/13/2026 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 4/13/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/22/2026 | Approved | JEFFREY HARTLINE |