12426 W ALBERS ST 91607

Certificate Information: 12426 W ALBERS ST 91607

Application / Permit
22014-20000-04130
Plan Check / Job No.
B22VN12516
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Remodel existing 1,459 S.F. 3BD 2 BTH SFR to a 1,936 S.F. 3BD 3.5 BTH SFR.
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 JAD BASMA
Corrections Issued 8/28/2022 JAD BASMA
Quality Review Completed 9/7/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 10/31/2022 JAD BASMA
Issued 2/28/2023 APPLICANT
CofO in Progress 6/19/2024 JOHN COLEMAN
Permit Finaled 7/2/2024 RUBEN SALAS
CofO Issued 7/2/2024 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 9/15/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 9/16/2022 JOSE DUARTE-DIAZ
Specific Plan Cleared 9/27/2022 CORREY KITCHENS
Low Impact Development Cleared 10/21/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/27/2022 ROMAN GUTIERREZ

Contact Information

Contractor Empire Construction Services Inc; Lic. No.: 1077736-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: NA26962       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 4/26/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/23/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/6/2023 Corrections Issued JUAN VALENZUELA
HVAC-Rough 10/6/2023 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 10/6/2023 Partial Approval JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Not Ready KIRK SANDERS
Rough-Elec/Plmb/HVAC 11/7/2023 No Access for Inspection KIRK SANDERS
Shower Pan 11/7/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/28/2023 Not Ready for Inspection KIRK SANDERS
Rough-Elec/Plmb/HVAC 11/28/2023 Not Ready for Inspection KIRK SANDERS
Shower Pan 11/28/2023 Not Ready for Inspection KIRK SANDERS
Wood Frame 11/28/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 11/30/2023 Approved CHRISTOPHER ROJAS
Insulation 11/30/2023 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 11/30/2023 Approved CHRISTOPHER ROJAS
Shower Pan 11/30/2023 Approved CHRISTOPHER ROJAS
Drywall Nailing 12/8/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 2/23/2024 Corrections Issued JOSE AVILA
HVAC-Final 2/23/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/23/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 2/23/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 2/27/2024 Corrections Issued JOSE AVILA
Final 4/4/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/4/2024 Approved JOSE AVILA
Smoke Detectors 4/4/2024 Approved JOSE AVILA
Final 6/14/2024 Partial Inspection JOHN COLEMAN
Final 6/18/2024 Off-Hour Fees Due
Final 6/20/2024 OK to Issue CofO JOHN COLEMAN