10039 N COLLETT AVE 91343
Certificate Information: 10039 N COLLETT AVE 91343
- Application / Permit
- 22014-20000-04127
- Plan Check / Job No.
- B22VN12508
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (17' X 8' ) TO EX. SFD FOR NEW CLOSET AND BATHROOM. WORK PER WFPP.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2022 | JESSE ARELLANO |
| Corrections Issued | 8/16/2022 | JESSE ARELLANO |
| Plan Check Approved | 9/7/2022 | ROSENDO MEDINA |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 5/22/2025 | CHRISTOPHER ROJAS |
| CofO Issued | 5/23/2025 | RUBEN SALAS |
| Permit Finaled | 5/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 9/1/2022 | LANNY MERRICK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2022 | Conditional Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 9/16/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 10/3/2022 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/3/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 10/3/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/3/2022 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/3/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 10/3/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 10/3/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 10/7/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/7/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/7/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 10/7/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/7/2022 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/17/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Not Ready | JAVIER RAMOS JR |
| Final | 10/31/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/31/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/31/2022 | Corrections Issued | JAVIER RAMOS JR |
| Final | 11/14/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 11/14/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 5/22/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Rough | 5/22/2025 | Approved | CHRISTOPHER ROJAS |