13118 W BLYTHE ST 91605

Certificate Information: 13118 W BLYTHE ST 91605

Application / Permit
22014-20000-04109
Plan Check / Job No.
B22VN12443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN NEW 304.6 SF ADDITION TO EXISTING HOUSE, EXISTING 343.6 SF GARAGE TO BE CONVERTED TO NEW ADDITION TO EXISTING HOUSE, NEW 400.0 SF 2-CAR ATTACHED GARAGE, REMODELING EXISTING HOUSE. NEW 322.5 SQ. FT. COVERED PATIO ATTACHED AT REAR
Permit Issued
Issued on 5/22/2023
Issuing Office
Current Status
CofO Issued on 10/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 JAD BASMA
Corrections Issued 9/8/2022 JAD BASMA
Quality Review Completed 9/9/2022 GARO TELMI
Applicant returned to address corrections 5/10/2023 JAD BASMA
Plan Check Approved 5/11/2023 JAD BASMA
Issued 5/22/2023 APPLICANT
CofO in Progress 10/10/2024 GREGG CUMMINGS
CofO Issued 10/28/2024 DANIEL ORRANTE
Permit Finaled 10/28/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 4/12/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/14/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/17/2023 COLIN LOREDO
Sewer availability Cleared 4/26/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/14/2023 Conditional Approval DAVID MATSON
PLUMBING-Rough 9/15/2023 Partial Approval DAVID MATSON
Underground Mechanical 9/15/2023 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 9/18/2023 Corrections Issued GREGG CUMMINGS
Sewer 10/5/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 1/16/2024 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 1/16/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 1/16/2024 Approved GREGG CUMMINGS
Insulation 1/16/2024 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 1/16/2024 Partial Approval GREGG CUMMINGS
Sewer 1/16/2024 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval GREGG CUMMINGS
Underground Mechanical 1/18/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 4/11/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval GREGG CUMMINGS
HVAC-Rough 4/11/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 4/11/2024 Approved GREGG CUMMINGS
Shower Pan 4/11/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/15/2024 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 4/15/2024 Approved GREGG CUMMINGS
Green Building Rough 4/15/2024 Approved GREGG CUMMINGS
Insulation 4/18/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/18/2024 Partial Approval GREGG CUMMINGS
Drywall Nailing 4/24/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 5/15/2024 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 10/1/2024 Approved GREGG CUMMINGS
Final 10/1/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/1/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 10/1/2024 Approved GREGG CUMMINGS
Final 10/4/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/4/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 10/9/2024 Approved GREGG CUMMINGS
Final 10/9/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/9/2024 Approved GREGG CUMMINGS
PLUMBING-Final 10/9/2024 Approved GREGG CUMMINGS
Service/Power Release 10/9/2024 Approved GREGG CUMMINGS