1582 N SORRENTO DR 90272

Certificate Information: 1582 N SORRENTO DR 90272

Application / Permit
22014-20000-04085
Plan Check / Job No.
B22VN12395
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND IRR SHAPED ADDITION (258 SF) AT REAR OF (E) SFD AND (N) OPEN TRELLIS; ALL WORK PER ENG. DESIGN
Permit Issued
Issued on 5/11/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 SEAN SHAHMIRI
Corrections Issued 8/22/2022 SEAN SHAHMIRI
Quality Review Completed 8/25/2022 OMID HEDAYAT
Building Plans Picked Up 8/26/2022 APPLICANT
Plan Check Approved 9/19/2022 SEAN SHAHMIRI
Issued 5/11/2023 APPLICANT
Permit Finaled 5/31/2024 DANIEL ORRANTE
CofO Issued 5/31/2024 DANIEL ORRANTE
Permit Finaled 5/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/27/2022 STEVEN JIN
Sewer availability Cleared 8/27/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 8/29/2022 KATHLEEN LEE
Hydrant and Access approval Cleared 9/20/2022 GILBERT URREA

Contact Information

Architect Joslin,, Timothy C; Lic. No.: C33261 1172 N HACIENDA PLACE # 20      WEST HOLLYWOOD, CA 90069
Contractor Owner-Builder       ,
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28611 HASKELL CANYON RD      SANTA CLARITA, CA 91390

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/5/2023 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/14/2023 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 6/14/2023 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 6/27/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval KEVIN SARGSYAN
Wood Frame 8/14/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/31/2023 Approved KEVIN SARGSYAN
HVAC-Rough 8/31/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 9/8/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/11/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/13/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/13/2023 Partial Approval KEVIN SARGSYAN
Shower Pan 10/13/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/19/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 10/20/2023 Approved KEVIN SARGSYAN
Green Building Rough 10/20/2023 Approved KEVIN SARGSYAN
Insulation 10/23/2023 Approved KEVIN SARGSYAN
Drywall Nailing 10/24/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 5/14/2024 Approved KENNETH NAGLE
HVAC-Final 5/14/2024 Approved KENNETH NAGLE
PLUMBING-Final 5/14/2024 Approved KENNETH NAGLE
Final 5/15/2024 Corrections Issued KENNETH NAGLE
Green Building Final 5/15/2024 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved KENNETH NAGLE
Smoke Detectors 5/15/2024 Approved KENNETH NAGLE
Final 5/31/2024 Conditional Approval KENNETH NAGLE