2308 N HILLHURST AVE 90027
Certificate Information: 2308 N HILLHURST AVE 90027
- Application / Permit
- 22014-20000-04077
- Plan Check / Job No.
- B22VN12377
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 5'8" x 8'10" FULL BATH (EXTERIOR ACCESS ONLY) FOR POOL
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | JEFFREY TANGONAN |
| Corrections Issued | 8/12/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 9/19/2022 | MINA HABILI |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 5/6/2024 | JOSEPH MCGARRY |
| CofO Issued | 5/16/2024 | DEROLD HAUFF |
| Permit Finaled | 5/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/20/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 9/9/2022 | KIRK LINKLATER |
| Miscellaneous | Cleared | 9/14/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/19/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/25/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| Green Building Rough | 2/21/2023 | Approved | CHARLES BOGHOSKHAN |
| Rough-Elec/Plmb/HVAC | 2/21/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| Wood Frame | 2/21/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 3/6/2023 | Approved | JEFFREY MEAD |
| Wood Frame | 3/6/2023 | Approved | JEFFREY MEAD |
| Insulation | 3/14/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 3/14/2023 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/21/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 4/19/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/26/2023 | Approved | JOSEPH MCGARRY |
| Final | 4/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 4/26/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 4/26/2024 | Approved | JOSEPH MCGARRY |
| Final | 4/30/2024 | OK to Issue CofO | JOSEPH MCGARRY |