6905 N ENCINO AVE 91406
Certificate Information: 6905 N ENCINO AVE 91406
- Application / Permit
- 22014-20000-04076
- Plan Check / Job No.
- B22VN12372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15' X 15' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2022 | JESSE ARELLANO |
| Corrections Issued | 8/17/2022 | JESSE ARELLANO |
| Plan Check Approved | 12/10/2022 | JEROME MAGAT PALMA |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 7/3/2023 | JON MCHUGH |
| Permit Finaled | 7/14/2023 | JOHN JANSON |
| CofO Issued | 7/14/2023 | JOHN JANSON |
| Permit Finaled | 7/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/18/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/22/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/27/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/19/2023 | Conditional Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 1/24/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 2/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 2/14/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 2/14/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 4/4/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 4/4/2023 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 4/4/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/4/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 4/17/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/17/2023 | Approved | JON MCHUGH |
| Insulation | 4/17/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/17/2023 | Approved | JON MCHUGH |
| Shower Pan | 4/17/2023 | Approved | JON MCHUGH |
| Sewer | 6/1/2023 | Approved | JON MCHUGH |
| Final | 6/14/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 6/14/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 6/14/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/3/2023 | Approved | JON MCHUGH |
| Final | 7/3/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 7/3/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/3/2023 | Approved | JON MCHUGH |