6905 N ENCINO AVE 91406

Certificate Information: 6905 N ENCINO AVE 91406

Application / Permit
22014-20000-04076
Plan Check / Job No.
B22VN12372
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15' X 15' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2022 APPLICANT
Assigned to Plan Check Engineer 8/16/2022 JESSE ARELLANO
Corrections Issued 8/17/2022 JESSE ARELLANO
Plan Check Approved 12/10/2022 JEROME MAGAT PALMA
Issued 12/19/2022 APPLICANT
CofO in Progress 7/3/2023 JON MCHUGH
Permit Finaled 7/14/2023 JOHN JANSON
CofO Issued 7/14/2023 JOHN JANSON
Permit Finaled 7/14/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/18/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/18/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/22/2022 COLIN LOREDO
Sewer availability Cleared 8/22/2022 COLIN LOREDO
Construction near power lines Cleared 10/27/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/19/2023 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 1/24/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 2/8/2023 Not Ready for Inspection JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/14/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 2/14/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/4/2023 Approved SEAN HAUPT
ELECTRICAL-Rough 4/4/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Approved SEAN HAUPT
Green Building Rough 4/4/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 4/4/2023 Approved SEAN HAUPT
PLUMBING-Rough 4/4/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/17/2023 Approved JON MCHUGH
Drywall Nailing 4/17/2023 Approved JON MCHUGH
Green Building Rough 4/17/2023 Approved JON MCHUGH
Insulation 4/17/2023 Approved JON MCHUGH
Interior/Exterior Lathing 4/17/2023 Approved JON MCHUGH
Shower Pan 4/17/2023 Approved JON MCHUGH
Sewer 6/1/2023 Approved JON MCHUGH
Final 6/14/2023 Corrections Issued JON MCHUGH
Green Building Final 6/14/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved JON MCHUGH
Smoke Detectors 6/14/2023 Approved JON MCHUGH
ELECTRICAL-Final 7/3/2023 Approved JON MCHUGH
Final 7/3/2023 OK to Issue CofO JON MCHUGH
HVAC-Final 7/3/2023 Approved JON MCHUGH
PLUMBING-Final 7/3/2023 Approved JON MCHUGH