5510-5512 N RHODES AVE 91607

Certificate Information: 5510-5512 N RHODES AVE 91607

Application / Permit
22014-20000-04067
Plan Check / Job No.
B22VN12369
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE WITH NEW SECOND FLOOR ADDITION INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 1/16/2023
Issuing Office
Current Status
CofO Issued on 6/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 KEVIN MORALES
Corrections Issued 9/2/2022 KEVIN MORALES
Quality Review Completed 9/6/2022 EUGENE BARBEAU
Plan Check Approved 10/24/2022 KEVIN MORALES
Issued 1/16/2023 APPLICANT
CofO in Progress 4/22/2024 JOSE AVILA
Permit Finaled 6/22/2024 RUBEN SALAS
CofO Issued 6/22/2024 RUBEN SALAS
Permit Finaled 6/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/21/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/21/2022 CARLOS AGUILERA
Specific Plan Cleared 10/12/2022 CORREY KITCHENS
Eng Process Fee Ord 176,300 Cleared 10/14/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/14/2022 ROMAN GUTIERREZ

Contact Information

Contractor Villagran Construction; Lic. No.: 910176-B       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: NA44672       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 2/10/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 3/15/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 5/19/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/19/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 6/15/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 6/15/2023 Conditional Approval KIRK SANDERS
PLUMBING-Rough 6/15/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 6/23/2023 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 6/27/2023 Off-Hour Fees Due
BUILDING-Rough-Frame 6/28/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/28/2023 Off-Hour Fees Due
Interior/Exterior Lathing 6/28/2023 Partial Approval JUAN VALENZUELA
Insulation 7/6/2023 Approved JUAN VALENZUELA
Insulation 7/6/2023 Off-Hour Fees Due
Shower Pan 7/6/2023 Approved JUAN VALENZUELA
Shower Pan 7/6/2023 Off-Hour Fees Due
Drywall Nailing 7/13/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/13/2023 Approved KIRK SANDERS
ELECTRICAL-Final 2/15/2024 Corrections Issued JOSE AVILA
HVAC-Final 2/15/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/15/2024 Corrections Issued JOSE AVILA
Special/Order Compliance 3/20/2024 Corrections Issued KIRK SANDERS
HVAC-Final 4/15/2024 Approved JOSE AVILA
PLUMBING-Final 4/15/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 4/18/2024 Approved JOSE AVILA
Final 4/18/2024 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 4/18/2024 Approved JOSE AVILA
Service/Power Release 5/28/2024 Approved JOSE AVILA