633 W 58TH ST 90037

Certificate Information: 633 W 58TH ST 90037

Application / Permit
22014-20000-04054
Plan Check / Job No.
B22VN10003
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan ADD TWO-STORY TYPE VB ADU TO AN EXISTING ONE CAR GARAGE PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 2/11/2023
Issuing Office
Current Status
CofO Issued on 1/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 QUAN NGHIEM
Corrections Issued 8/11/2022 QUAN NGHIEM
Quality Review Completed 8/16/2022 CHAD DOI
Applicant returned to address corrections 8/24/2022 QUAN NGHIEM
Applicant returned to address corrections 11/29/2022 QUAN NGHIEM
Plan Check Approved 2/9/2023 QUAN NGHIEM
Issued 2/11/2023 APPLICANT
CofO in Progress 1/3/2024 ENRIQUE MIRELES
Permit Finaled 1/7/2024 DEROLD HAUFF
CofO Issued 1/7/2024 DEROLD HAUFF
Permit Finaled 1/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/19/2022 STEVE MELGAR
Sewer availability Cleared 8/19/2022 STEVE MELGAR
Low Impact Development Cleared 11/22/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 11/26/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/12/2023 Approved SABAS ALONSO
Underground Mechanical 4/12/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 4/21/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/4/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/4/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/4/2023 Approved SABAS ALONSO
HVAC-Rough 8/4/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/4/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/21/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 8/21/2023 Approved SABAS ALONSO
Green Building Rough 8/21/2023 Approved SABAS ALONSO
Insulation 8/23/2023 Partial Approval SABAS ALONSO
Drywall Nailing 8/31/2023 Approved SABAS ALONSO
Insulation 8/31/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 9/18/2023 Approved SABAS ALONSO
Shower Pan 9/18/2023 Not Ready for Inspection SABAS ALONSO
Shower Pan 9/20/2023 Approved SABAS ALONSO
ELECTRICAL-Final 11/27/2023 Corrections Issued RONNIE MINDANAO
HVAC-Final 11/27/2023 Corrections Issued RONNIE MINDANAO
PLUMBING-Final 11/27/2023 Corrections Issued RONNIE MINDANAO
Service/Power Release 11/27/2023 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 11/27/2023 Approved RONNIE MINDANAO
Final 12/7/2023 Corrections Issued CRAIG DAVIS
Green Building Final 12/7/2023 Approved CRAIG DAVIS
HVAC-Rough 12/7/2023 Approved CRAIG DAVIS
PLUMBING-Final 12/7/2023 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Not Ready CRAIG DAVIS
ELECTRICAL-Final 12/19/2023 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 12/19/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 12/19/2023 Corrections Issued ENRIQUE MIRELES
Final 1/2/2024 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 1/2/2024 Approved ENRIQUE MIRELES