10363 W MCCORMICK ST 91601
Certificate Information: 10363 W MCCORMICK ST 91601
- Application / Permit
- 22014-20000-03979
- Plan Check / Job No.
- B22VN12103
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan PROPOSED 14-7" x 10'-4" ADDITION TO AND CONVERT THE (E) 17'-7" x 20'-2" DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT AND STORAGE PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 8/13/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/31/2022 | OMAR GARNICA |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 1/29/2024 | JOHN HAYES |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/31/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/1/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/28/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/13/2023 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 1/20/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/25/2023 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/3/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 3/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/16/2023 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/16/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 3/16/2023 | Partial Approval | JOHN COLEMAN |
| Sewer | 3/16/2023 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 4/7/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 4/13/2023 | Partial Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 4/13/2023 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/17/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/17/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 4/17/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 4/17/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 4/21/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | JOHN COLEMAN |
| Drywall Nailing | 4/26/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/13/2023 | Approved | JOHN HAYES |
| Final | 9/13/2023 | Corrections Issued | JOHN HAYES |
| HVAC-Final | 9/13/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 9/13/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 9/28/2023 | Approved | JOHN HAYES |
| Final | 9/28/2023 | Corrections Issued | JOHN HAYES |
| HVAC-Final | 9/28/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 9/28/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/4/2023 | Approved | MISAEL ESPARZA |
| Final | 10/4/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/4/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 10/4/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/11/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 10/11/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/11/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/14/2023 | Corrections Issued | ROBERT GOLD |
| Final | 1/26/2024 | OK to Issue CofO | JOHN HAYES |