10363 W MCCORMICK ST 91601

Certificate Information: 10363 W MCCORMICK ST 91601

Application / Permit
22014-20000-03979
Plan Check / Job No.
B22VN12103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan PROPOSED 14-7" x 10'-4" ADDITION TO AND CONVERT THE (E) 17'-7" x 20'-2" DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT AND STORAGE PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/2/2022
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 SARKIS HARABEDIAN
Corrections Issued 8/13/2022 SARKIS HARABEDIAN
Plan Check Approved 10/31/2022 OMAR GARNICA
Issued 11/2/2022 APPLICANT
CofO in Progress 1/29/2024 JOHN HAYES
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/31/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/31/2022 COLIN LOREDO
Sewer availability Cleared 9/1/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/18/2022 COLIN LOREDO
Construction near power lines Cleared 10/28/2022 RIDWAN HARDY

Contact Information

Contractor Build Method Construction Inc; Lic. No.: 1059684-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/13/2023 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 1/20/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 1/20/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 1/25/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 3/3/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 3/16/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 3/16/2023 Approved JOHN COLEMAN
Footing/Foundation/Slab 3/16/2023 Partial Approval JOHN COLEMAN
PLUMBING-Rough 3/16/2023 Partial Approval JOHN COLEMAN
Sewer 3/16/2023 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval CHRISTOPHE COCHRAN
Insulation 4/7/2023 Corrections Issued MISAEL ESPARZA
Insulation 4/13/2023 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 4/13/2023 Partial Inspection ROBERT GOLD
BUILDING-Rough-Frame 4/17/2023 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 4/17/2023 Corrections Issued CHRISTOPHE COCHRAN
Insulation 4/17/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/17/2023 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 4/17/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/21/2023 Approved JOHN COLEMAN
HVAC-Rough 4/21/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 4/21/2023 Partial Approval JOHN COLEMAN
Drywall Nailing 4/26/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/25/2023 Corrections Issued JENNIFER RABUCHIN
Final 7/25/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/25/2023 Approved JENNIFER RABUCHIN
HVAC-Final 7/25/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/25/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/25/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/25/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/2/2023 Approved JENNIFER RABUCHIN
Final 8/2/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 8/2/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/2/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/21/2023 Approved JENNIFER RABUCHIN
Final 8/21/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 8/21/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/21/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/13/2023 Approved JOHN HAYES
Final 9/13/2023 Corrections Issued JOHN HAYES
HVAC-Final 9/13/2023 Approved JOHN HAYES
PLUMBING-Final 9/13/2023 Approved JOHN HAYES
ELECTRICAL-Final 9/28/2023 Approved JOHN HAYES
Final 9/28/2023 Corrections Issued JOHN HAYES
HVAC-Final 9/28/2023 Approved JOHN HAYES
PLUMBING-Final 9/28/2023 Approved JOHN HAYES
ELECTRICAL-Final 10/4/2023 Approved MISAEL ESPARZA
Final 10/4/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 10/4/2023 Approved MISAEL ESPARZA
PLUMBING-Final 10/4/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/11/2023 Approved JENNIFER RABUCHIN
Final 10/11/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 10/11/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/11/2023 Approved JENNIFER RABUCHIN
Final 11/14/2023 Corrections Issued ROBERT GOLD
Final 1/26/2024 OK to Issue CofO JOHN HAYES