6715-6717 N KATHERINE AVE 91405

Certificate Information: 6715-6717 N KATHERINE AVE 91405

Application / Permit
22014-20000-03975
Plan Check / Job No.
B22VN12101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan NEW ATTACHED TWO STORY ACCESSORY DWELLING UNIT TO EXISTING SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 11/21/2022
Issuing Office
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/26/2022 SELLA BENYAMIN
Corrections Issued 8/31/2022 SELLA BENYAMIN
Quality Review Completed 9/13/2022 STEVEN KIM
Applicant returned to address corrections 11/10/2022 SELLA BENYAMIN
Plan Check Approved 11/17/2022 SELLA BENYAMIN
Issued 11/21/2022 APPLICANT
CofO in Progress 8/25/2023 RYAN SALAZAR
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/25/2022 CARLOS AGUILERA
HPOZ Cleared 10/26/2022 DANIEL MATA
Eng Process Fee Ord 176,300 Cleared 10/27/2022 CARLOS AGUILERA
Sewer availability Cleared 10/27/2022 CARLOS AGUILERA
Low Impact Development Cleared 10/28/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/28/2022 CARLOS AGUILERA

Contact Information

Contractor D B Builders Inc; Lic. No.: 812896-B       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2022 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 1/25/2023 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 1/25/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 2/2/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/17/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/15/2023 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/3/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 4/3/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/7/2023 Approved RYAN SALAZAR
HVAC-Rough 4/7/2023 Approved RYAN SALAZAR
PLUMBING-Rough 4/7/2023 Approved RYAN SALAZAR
Insulation 4/17/2023 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 4/17/2023 Partial Approval JOHN COLEMAN
Drywall Nailing 4/27/2023 Approved RYAN SALAZAR
Service/Power Release 5/16/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 8/24/2023 Approved RYAN SALAZAR
Final 8/24/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 8/24/2023 Approved RYAN SALAZAR
PLUMBING-Final 8/24/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 8/24/2023 Approved RYAN SALAZAR
Smoke Detectors 8/24/2023 Approved RYAN SALAZAR